residential Ready to Move Source: rera.mh

DA Om Sai Avenue RERA Details - P51700054556, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for DA Om Sai Avenue under registration P51700054556 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700054556
  • Project Name OM SAI AVENUE
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Ambarnath(M Cl)
  • Original Completion 31 December 2025
  • Revised Completion 31 December 2025
  • Project Area (in Sq.mt.) 562.5
  • Total Buildings/Towers 1
  • Documents 36 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 31 January 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name D A CONSTRUCTION
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
KARISHMA APARTMENTPLOT NO 12 GUT NO 57 VILLAGE MORIVALI B CABIN ROAD AMBERNATH EAST729CompletedResidential / Group Housing1202007-03-312007-03-31NoNA
KARISHMA APARTMENTPLOT NO.10 GUT NO.57 VILLAGE MORIVALI B CABIN ROAD AMBERNATH EAST725CompletedResidential / Group Housing1182007-03-312007-03-31NoNA
SAI RESIDENCYGUT NO.52P NAVRE NAGAR MORIVALI AMBERNATH EAST3900CompletedResidential / Group Housing3762008-03-312008-06-10NoNA
KRISH APARTMENTPLOT NO 16 GUT NO 46-3 BEHIND NAVRE NAGAR MORIVALI AMBERNATH EAST354CompletedResidential / Group Housing182011-02-012011-06-01NoNA
KRISH APARTMENTPLOT NO.17 GUT NO.46-3 BEHIND NAVRE NAGAR MORIVALI AMBERNATH EAST372CompletedResidential / Group Housing1112011-03-312011-06-01NoNA
KRISH APARTMENTPLOT NO 18 AND 19 GUT NO.46-3 BEHIND NAVRE NAGAR MORIVALI AMBERNATH EAST792CompletedResidential / Group Housing1192011-05-012011-07-01NoNA
OM SAI APARTMENTCTS NO 9008 GUT NO.61-1 B CABIN ROAD MORIVALI AMBERNATH EAST1000CompletedResidential / Group Housing1192012-05-012012-05-01NoNA
SHANI SOHAM APARTMENTCTS NO 9299-5 MORIVALI GAONTHAN AMBERNATH EAST1149.7CompletedResidential / Group Housing2452013-05-012013-07-01NoNA
SAI RAKSHA APARTMENTPLOT NO 5-6-7 SURVEY NO 84 CTS NO 9265 NEAR RELIANCE RESIDENCY AMBERNATH EAST746CompletedResidential / Group Housing1172015-01-012015-01-01NoNA
OM SAI NATH APARTMENTSURVEY NO 33 HISSA NO 7P CTS NO 8967 - 8968 NEAR MAHALAXMI NAGAR VILLAGE VADAVALI AMBERNATH EAST451.5CompletedResidential / Group Housing1142015-11-012015-12-01NoNA

Promoters, Co-promoters & Members

NameRoleAddress
SHARAD JAYANTILAL DESAIPartnerMumbai City, MAHARASHTRA
AKHIL ANIL DESAIAUTHORISED PARTNERMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
OM SAI AVENUE OM SAI AVENUE 22 28 8 8 7 19 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 19
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 12 units · avg area 57.77 Sq.mt.
3 BHK 7 units · avg area 66.43 Sq.mt.
  • OM SAI AVENUE
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 57.64 6 0
2BHK 57.9 6 0
3BHK 79.48 1 0
3BHK 64.26 6 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains % not reported Landscaping & Tree Planting 100.0% Street Lighting 100.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • OM SAI AVENUE
OM SAI AVENUE · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

15 1 CERSAI Details.Pdf
16 2 CERSAI Details.Pdf
Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 B Details Of Encumbrances Concerned To Legal.Pdf
6 2 B Details Of Encumbrances Concerned To Legal.Pdf
7 1 Copy Of Layout Approval (In Case Of Layout).Pdf
8 1 Building Plan Approval NA Order For Plotted Development.Pdf
9 1 Commencement Certificates NA Order For Plotted Development.Pdf
10 2 Commencement Certificates NA Order For Plotted Development.Pdf
11 1 Declaration About Commencement Certificate.Pdf
12 1 Declaration In FORM B.Pdf
13 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
14 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
17 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
18 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
19 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
20 1 Proforma Of Allotment Letter.Pdf
21 1 Proforma Of Agreement For Sale.Pdf
22 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
23 1 Deviation Report With Respect To Allotment Letter.Pdf
24 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
25 1 Other – Technical.Pdf
26 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
27 Form 1.Pdf
28 Form 2.Pdf
29 Form 3.Pdf
30 Disclosure Of Sold And Booked Inventory.Pdf
47 Form 2A (FY 2023 2024).Pdf
48 Form 2A (FY 2024 2025).Pdf
49 Form 5 (FY 2023 2024).Pdf
50 Occupational Certificate.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BHARAT COOPERATIVE BANK MUMBAI LIMITED
IFSC BCBM0000074
Branch Address AMBERNATH EAST
Country/City