residential Under Construction Source: rera.mh

Shreeji Landmark RERA Details - P51700052645, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Shreeji Landmark under registration P51700052645 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700052645
  • Project Name SHREEJI LANDMARK PHASE II
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Badlapur (M Cl)
  • Original Completion 31 December 2026
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 3,129.0
  • Total Buildings/Towers 4
  • Documents 44 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 15 September 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Shubh Housing

Promoters, Co-promoters & Members

NameRoleAddress
VIPUL BHARATKUMAR SHAHPartnerThane, MAHARASHTRA
JAYESH BHERULAL JAINPartnerThane, MAHARASHTRA
JIGNESH BHARATBHAI SHAHPartneri85fr2lqtVAwW0JAWVeArf8lP7MMVyHhDLpL1ftJity/ML6Brk75PFMeqSyBuiIB, HCfEcBYIbJctMtfgKUXS4s/coY9B0fobUYIGIem6OEwEkJwawNObhGfHlF/xhp8I, Thane, MAHARASHTRA
MAHENDRA KUMAR CHAGANLAL JAINPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SHREEJI LANDMARK PHASE II WING B 60 0 8 7 7 40 NA
SHREEJI LANDMARK PHASE II WING C 61 0 8 7 7 41 NA
SHREEJI LANDMARK PHASE II WING D 42 0 8 7 7 28 NA
SHREEJI LANDMARK PHASE II WING E 3 0 2 1 1 2 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 111
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 82 units · avg area 31.51 Sq.mt.
2 BHK 29 units · avg area 43.25 Sq.mt.
  • WING B
  • WING C
  • WING D
  • WING E
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 33.31 7 4
2BHK 43.07 6 2
1BHK 30.0 13 2
2BHK 42.86 14 5
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • WING B
  • WING C
  • WING D
  • WING E
WING B · Overall Progress 76%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work40%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 1 A Details Of Encumbrances Concerned To Finance.Pdf
5 2 A Details Of Encumbrances Concerned To Finance.Pdf
6 3 A Details Of Encumbrances Concerned To Finance.Pdf
7 1 B Details Of Encumbrances Concerned To Legal.Pdf
8 2 B Details Of Encumbrances Concerned To Legal.Pdf
9 3 B Details Of Encumbrances Concerned To Legal.Pdf
10 1 Copy Of Layout Approval (In Case Of Layout).Pdf
11 1 Building Plan Approval NA Order For Plotted Development.Pdf
12 2 Building Plan Approval NA Order For Plotted Development.Pdf
13 3 Building Plan Approval NA Order For Plotted Development.Pdf
14 4 Building Plan Approval NA Order For Plotted Development.Pdf
15 1 Commencement Certificates NA Order For Plotted Development.Pdf
16 1 Declaration About Commencement Certificate.Pdf
17 1 Declaration In FORM B.Pdf
18 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
19 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
20 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
21 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
22 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
23 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
24 1 CERSAI Details.Pdf
25 2 CERSAI Details.Pdf
26 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
27 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
28 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
29 3 Disclosure Of Interest In Other Real Estate Organizations.Pdf
30 4 Disclosure Of Interest In Other Real Estate Organizations.Pdf
31 1 Proforma Of Allotment Letter.Pdf
32 1 Proforma Of Agreement For Sale.Pdf
33 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
34 2 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
35 1 Deviation Report With Respect To Allotment Letter.Pdf
36 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
37 1 Other – Finance.Pdf
43 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
46 Withdrawal Update Form 1.Pdf
50 Withdrawal Update Form 2.Pdf
54 Withdrawal Update Form 3.Pdf
58 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0001806
Branch Address PLOT NO 51 VED BUNGLOW NEAR OLD TALATHI OFFICE KULGAON BADLAPUR EAST 421503
Country/City