residential Ready to Move Source: rera.mh

Audumbar CHS Vile RERA Details - P51800015235, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Audumbar CHS Vile under registration P51800015235 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800015235
  • Project Name AUDUMBAR CHS LTD
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Andheri
  • Village Andheri
  • Original Completion 30 March 2022
  • Revised Completion 30 March 2022
  • Project Area (in Sq.mt.) 831.1
  • Total Buildings/Towers 1
  • Documents 17 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 08 February 2018 Expected commencement of civil works and foundation on site.
Original Completion 30 March 2022 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 March 2022 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name REGENT BUILDERS
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
RADHA RESIDENCYISMALIA VILLAGE SARASWAT BAUGJOGESHWARI EAST MUMBAI-400060673.1CompletedResidential / Group Housing1202016-03-312016-02-24NoNA

Promoters, Co-promoters & Members

NameRoleAddress
RAMESHCHAND BABULALJI BOHRAPartnerMumbai Suburban, MAHARASHTRA
KANWAL RAMESHCHAND BOHRAPartnerMumbai Suburban, MAHARASHTRA
KETAN RAMESHCHAND BOHRAPartnerMumbai Suburban, MAHARASHTRA
PRATIK HIRALAL BOHRAPartnerMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
AUDUMBAR CHS LTD AUDUMBAR CHS LTD 1 0 8 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 16
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 9 units · avg area 62.91 Sq.mt.
3 BHK 7 units · avg area 44.19 Sq.mt.
  • AUDUMBAR CHS LTD
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 69.77 3 2
2BHK 69.79 2 2
3BHK 89.37 1 1
3BHK 87.65 1 1
2BHK 68.21 1 1
2BHK 68.19 1 1
3BHK 20.35 4 4
2BHK 9.48 1 1
3bhk 50.91 1 1
2BHK 71.4 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • AUDUMBAR CHS LTD
AUDUMBAR CHS LTD · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Iod.Pdf.Pdf
2 Audumbar IOD Amended 1.Pdf.Pdf
3 Audumbar IOD Amended 2.Pdf.Pdf
4 2146018 IOD Signed FINAL.Pdf.Pdf
5 Page 1 A5 Small Min.Pdf.Pdf
6 Page 2 Small 2.Pdf.Pdf
7 Pan Card.Pdf.Pdf
8 Full OC.Pdf.Pdf
9 Drawing 1.Pdf.Pdf
10 Drawing 2.Pdf.Pdf
11 Architect Certificate On Completion Of Building.Pdf.Pdf
12 Title Page 1.Pdf.Pdf
13 Title 2.Pdf.Pdf
14 Form B Undertaking Audumbar.Pdf.Pdf
15 Audumbar Agreement Draft.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank RBL Bank Limited
IFSC RATN0000192
Branch Address SHOP NO 2 BALAJI BUSINESS PARK ANDHERI KURLA ROAD ANDHERI EAST MUMBAI-400059
Country/City