Dharmi Pixel RERA Details - P51800048077, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Dharmi Pixel under registration P51800048077 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800048077
  • Project Name PIXEL
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Kurla
  • Village Kurla
  • Original Completion 31 December 2028
  • Revised Completion 31 December 2028
  • Project Area (in Sq.mt.) 1,621.2
  • Total Buildings/Towers 1
  • Documents 14 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 08 December 2022 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name DHARMI PROPERTIES PVT LTD
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
MAHAVIR KRUPA CHSL353B-22 23 VALLABH BAUG LANE GHATKOPAR EAST MUMBAI 4000771065CompletedResidential / Group Housing1472018-12-312018-10-30NoNA

Promoters, Co-promoters & Members

NameRoleAddress
JIGNESH VINODRAI SHAHDirectorMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
PIXEL PIXEL 84 1 20 16 16 1 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units -
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
3 BHK 0 units
  • PIXEL
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area No. of Unit Balance Amount Consideration Floor Type Query Raised Residential Received Amount Reckoner Rate Status Transaction Mode
Floor 16 3 BHK 987.0 G+16 ₹0 ₹0 Habitable Floor Clear Residential ₹0 18,000 Unsold None
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 25.0% Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains 75.0% Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal 20.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 40.0%
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • PIXEL
PIXEL · Overall Progress 69%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work40%
Sanitary Fittings within the flats / premises
In Progress
% Work25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work30%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Neelkanth Dhara Approved IOD.Pdf.Pdf
2 ND IOD Drawing 1.Pdf.Pdf
3 Final Airport Authority NOC.Pdf.Pdf
4 Charge Registration Certificate Dharmi.Pdf.Pdf
5 PAN Card Dharmi Properties.Pdf.Pdf
6 High Court Order.Pdf.Pdf
7 Legal Title Report Format A.Pdf.Pdf
8 Form B.Pdf.Pdf
9 Rera Draft Allotment Letter.Pdf.Pdf
10 Deviation Report With Respect To Allotment Letter.Pdf.Pdf
11 RERA Model Agr.Pdf.Pdf
12 Deviation Report With Respect To Model Copy Of Agreement.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0000118
Branch Address SHOP NO 1 AND 2, BHAVESHWAR BLDG NO 3, BHAVESHWAR LANE, GHATKOPAR EAST, MUMBAI-400077
Country/City