Harshail Hornbill RERA Details - P51800029350, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Harshail Hornbill under registration P51800029350 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800029350
  • Project Name HARSHAIL HORNBILL APARTMENT
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Borivali
  • Village Borivali
  • Original Completion 31 December 2026
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 2,013.4
  • Total Buildings/Towers 1
  • Documents 15 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 18 May 2021 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name ROSEFINCH DEVELOPERS LLP

Promoters, Co-promoters & Members

NameRoleAddress
APURVA DHRUVKUMAR DESAIChairpersonMumbai City, MAHARASHTRA
PRAVIN LALLUBHAI DESAIManaging DirectorMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
HARSHAIL HORNBILL APARTMENT HARSHAIL HORBILL APARTMENT 1 1 22 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 99
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1RK 2 units · avg area 18.02 Sq.mt.
1 BHK 95 units · avg area 31.19 Sq.mt.
2 BHK 1 unit · avg area 43.66 Sq.mt.
Shop 1 unit · avg area 22.32 Sq.mt.
  • HARSHAIL HORBILL APARTMENT
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 22.32 1 0
1RK 16.72 1 1
2BHK 43.66 1 1
1BHK 31.12 78 77
1BHK 31.49 17 17
1RK 19.32 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 75.0%
Storm Water Drains 75.0% Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 75.0%
Electrical Meter Room, Sub-station, Receiving Station 75.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • HARSHAIL HORBILL APARTMENT
HARSHAIL HORBILL APARTMENT · Overall Progress 79%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work70%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Plan 1.Pdf.Pdf
2 Plan 2.Pdf.Pdf
3 Plan 4.Pdf.Pdf
4 Plan 3.Pdf.Pdf
5 LOI Revised 27 10 21.Pdf.Pdf
6 LOI Revised Plan 27 10 21 Pg 1.Pdf.Pdf
7 LOI Revised Plan 27 10 21 Pg 2.Pdf.Pdf
8 LOI Revised Plan 27 10 21 Pg 3.Pdf.Pdf
9 Rosefich Developers LLP.Pdf.Pdf
10 Rosefinch Developers PDF.Pdf.Pdf
11 Declaration Revised Low Version.Pdf.Pdf
12 Title Certificate 14 5 21 Mark DMello.Pdf.Pdf
13 Self Declaration For RERA.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank STATE BANK OF INDIA
IFSC SBIN0004115
Branch Address SHYAM KAMAL TRADE CENTER B N AGRAWAL MARKET VILE PARLE EAST MUMBAI 400057