RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P51800053472
- Project Name MINAL AND MADHAVKUNJ
- Project Type Mixed
- Project Status Under Construction
- State Maharashtra
- District Mumbai Suburban
- Taluka Andheri
- Village Vileparle
- Original Completion 31 December 2026
- Revised Completion 31 December 2026
- Project Area (in Sq.mt.) 2,555.18
- Total Buildings/Towers 2
- Documents 20 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Address |
|---|---|
| Satish Kumar Saboo | Ranchi, JHARKHAND |
| Sandeep Satish Kumar Saboo | Mumbai Suburban, MAHARASHTRA |
| Fauzaan Ashraf Khan | Mumbai Suburban, MAHARASHTRA |
| Ashraf Maqbool Khan | Mumbai Suburban, MAHARASHTRA |
| Sumitra Devi Saboo | Ranchi, JHARKHAND |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | No. of Open Parking | No. of Closed Parking | No. of Floors | No. of Habitable Floor | No. of Sanctioned Apartment | Wing Name |
|---|---|---|---|---|---|---|---|
| MINAL AND MADHAVKUNJ | A Wing | 0 | 0 | 10 | 0 | 0 | NA |
| MINAL AND MADHAVKUNJ | B Wing | 0 | 0 | 12 | 0 | 0 | NA |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- A Wing
- B Wing
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| Rehab\3BHK | 98.16 | 1 | 1 |
| 2BHK | 60.11 | 4 | 3 |
| Rehab2BHK | 70.4 | 1 | 1 |
| 2BHK | 69.4 | 3 | 0 |
| Rehab2BHK | 69.4 | 1 | 1 |
| Rehab2BHK | 60.11 | 2 | 2 |
| Rehab2BHK | 58.81 | 1 | 1 |
| Rehab3BHK | 93.42 | 2 | 2 |
| Rehab3BHK | 82.88 | 1 | 1 |
| Rehab3BHK | 92.78 | 1 | 1 |
| Rehab3BHK | 77.45 | 1 | 1 |
| Shop | 42.47 | 1 | 0 |
| Shop | 43.88 | 1 | 0 |
| Shop | 24.05 | 1 | 0 |
| Shop | 21.04 | 1 | 0 |
| 2BHK | 55.38 | 6 | 1 |
| 2BHK | 70.4 | 2 | 0 |
| Rehab3BHK | 88.64 | 1 | 1 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| Shop Rehab | 17.31 | 1 | 1 |
| 2BHK | 73.44 | 1 | 1 |
| Shop Rehab | 36.46 | 1 | 1 |
| Shop Rehab | 19.94 | 1 | 1 |
| Shop Rehab | 22.99 | 1 | 1 |
| Rehab 3 BHK | 82.04 | 3 | 3 |
| Rehab 3 BHK | 79.7 | 1 | 1 |
| Rehab 3 BHK | 80.7 | 1 | 1 |
| Rehab 3 BHK | 165.47 | 1 | 1 |
| Shop Rehab | 21.79 | 1 | 1 |
| 1BHK | 43.72 | 1 | 0 |
| 1BHK | 39.73 | 1 | 0 |
| 2BHK | 60.11 | 1 | 0 |
| Shop Rehab | 16.7 | 1 | 1 |
| Shop Rehab | 14.98 | 1 | 1 |
| Shop Rehab | 20.72 | 1 | 1 |
| Rehab 2 BHK | 73.44 | 1 | 1 |
| Rehab 2 BHk | 70.45 | 1 | 1 |
| Rehab 2 BHK | 68.88 | 2 | 2 |
| Rehab 2 BHK | 65.2 | 1 | 1 |
| Rehab 1 BHK | 43.72 | 1 | 1 |
| Rehab 1 BHK | 41.38 | 1 | 1 |
| Rehab 1 BHK | 34.04 | 3 | 3 |
| MPRoom2\Rehab | 18.01 | 1 | 1 |
| Rehab 2 BHK | 64.44 | 1 | 1 |
| MPRoom1\Rehab | 21.84 | 1 | 1 |
| Rehab 3 BHK | 93.97 | 3 | 3 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads & Footpaths % not reported | Water Supply % not reported | Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported |
| Storm Water Drains % not reported | Landscaping & Tree Planting % not reported | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage And Sullage Water % not reported | Solid Waste Management And Disposal % not reported |
| Water Conservation /Rain Water Harvesting % not reported | Energy Managemcnt % not reported | Fire Protection And Fire Safety Requirements % not reported |
| Electrical Meter Room, Sub-station, Receiving Station % not reported | Aggregate Area Of Recreational Open Space % not reported | Open Parking % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- A Wing
- B Wing
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | STATE BANK OF INDIA |
|---|---|
| IFSC | SBIN0017293 |
| Branch Address | STATE BANK OF INDIA, PBB GOREGAON WEST BRANCH, BHOOMI CLASSIC CHSL, LINK ROAD, GOREGAON WEST, MUMBAI |