residential Ready to Move Source: rera.mh

Acons 54 Greens RERA Details - P52000013906, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Acons 54 Greens under registration P52000013906 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52000013906
  • Project Name Acons 54 Greens Phase 1
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Raigarh
  • Taluka Alibag
  • Village Khandale
  • Original Completion 20 March 2020
  • Revised Completion 20 March 2020
  • Project Area (in Sq.mt.) 3,140.0
  • Total Buildings/Towers 2
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 02 November 2017 Expected commencement of civil works and foundation on site.
Original Completion 20 March 2020 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 20 March 2020 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Individual

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Acons 54 Greens Phase 1 Acons 54 Greens Building 1 6 1 1 0 0 NA
Acons 54 Greens Phase 1 Acons 54 Greens Building 4 6 1 1 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 70
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1RK 34 units · avg area 22.68 Sq.mt.
1 RK 8 units · avg area 23.80 Sq.mt.
1 BHK 28 units · avg area 31.09 Sq.mt.
  • Acons 54 Greens Building 1
  • Acons 54 Greens Building 4
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1RK 21.79 16 9
1RK 22.03 6 5
1RK 23.72 6 4
1 RK 23.8 8 7
1RK 23.84 3 2
1RK 25.52 3 2
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains % not reported Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings 100.0% Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space 100.0% Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Acons 54 Greens Building 1
  • Acons 54 Greens Building 4
Acons 54 Greens Building 1 · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0000820
Branch Address Shreebag, Alibag
Country/City