Atharva My Element RERA Details - P52000028772, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Atharva My Element under registration P52000028772 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52000028772
  • Project Name MY ELEMENT
  • Project Type Mixed
  • Project Status Ready to Move
  • State Maharashtra
  • District Raigarh
  • Taluka Karjat
  • Village Kothimbe
  • Original Completion 30 June 2025
  • Revised Completion 30 June 2025
  • Project Area (in Sq.mt.) 63,050.0
  • Total Buildings/Towers 107
  • Documents 2 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 30 March 2021 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Individual
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
PARADISO BAY416-1 415 KIHIM ALIBAG11690CompletedResidential / Group Housing41922021-06-302021-06-30NoNA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
MY ELEMENT BUNGALOW-NO-3 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-5 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-6 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-8 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-9 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-10 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-13 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-14 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-17 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-18 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-19 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-20 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-21 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-22 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-25 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-26 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-27 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-28 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-29 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-30 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-31 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-32 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-36 1 0 2 0 0 NA
MY ELEMENT BUNAGLOW-NO-37 1 0 2 0 0 NA
MY ELEMENT BUNAGLOW-NO-38 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-39 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-1 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-41 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-42 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-2 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-43 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-4 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-44 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-11 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-45 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-12 1 0 2 0 0 NA
MY ELEMENT BUNAGLOW-NO-46 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-100 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-48 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-15 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-49 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-50 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-51 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-16 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-52 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-23 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-53 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-24 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-54 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-33 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-56 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-34 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-57 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-62 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-35 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-63 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-40 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-64 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-47 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-65 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-80 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-105 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-85 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-66 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-67 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-86 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-68 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-87 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-69 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-88 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-89 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-70 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-90 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-71 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-92 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-72 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-93 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-73 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-94 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-74 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-95 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-75 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-96 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-76 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-97 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-77 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-98 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-78 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-99 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-81 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-101 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-102 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-82 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-83 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-103 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-104 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-84 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-106 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-107 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-58 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-7 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-59 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-55 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-79 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-60 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-61 1 0 2 0 0 NA
MY ELEMENT BUNGALOW-NO-91 1 0 2 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 70.0% Water Supply 65.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 65.0%
Storm Water Drains 65.0% Landscaping & Tree Planting 50.0% Street Lighting 60.0%
Community Buildings 60.0% Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 65.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 70.0% Aggregate Area Of Recreational Open Space 65.0% Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BUNGALOW-NO-3
  • BUNGALOW-NO-5
  • BUNGALOW-NO-6
  • BUNGALOW-NO-8
  • BUNGALOW-NO-9
  • BUNGALOW-NO-10
  • BUNGALOW-NO-13
  • BUNGALOW-NO-14
  • BUNGALOW-NO-17
  • BUNGALOW-NO-18
  • BUNGALOW-NO-19
  • BUNGALOW-NO-20
  • BUNGALOW-NO-21
  • BUNGALOW-NO-22
  • BUNGALOW-NO-25
  • BUNGALOW-NO-26
  • BUNGALOW-NO-27
  • BUNGALOW-NO-28
  • BUNGALOW-NO-29
  • BUNGALOW-NO-30
  • BUNGALOW-NO-31
  • BUNGALOW-NO-32
  • BUNGALOW-NO-36
  • BUNAGLOW-NO-37
  • BUNAGLOW-NO-38
  • BUNGALOW-NO-39
  • BUNGALOW-NO-1
  • BUNGALOW-NO-41
  • BUNGALOW-NO-42
  • BUNGALOW-NO-2
  • BUNGALOW-NO-43
  • BUNGALOW-NO-4
  • BUNGALOW-NO-44
  • BUNGALOW-NO-11
  • BUNGALOW-NO-45
  • BUNGALOW-NO-12
  • BUNAGLOW-NO-46
  • BUNGALOW-NO-100
  • BUNGALOW-NO-48
  • BUNGALOW-NO-15
  • BUNGALOW-NO-49
  • BUNGALOW-NO-50
  • BUNGALOW-NO-51
  • BUNGALOW-NO-16
  • BUNGALOW-NO-52
  • BUNGALOW-NO-23
  • BUNGALOW-NO-53
  • BUNGALOW-NO-24
  • BUNGALOW-NO-54
  • BUNGALOW-NO-33
  • BUNGALOW-NO-56
  • BUNGALOW-NO-34
  • BUNGALOW-NO-57
  • BUNGALOW-NO-62
  • BUNGALOW-NO-35
  • BUNGALOW-NO-63
  • BUNGALOW-NO-40
  • BUNGALOW-NO-64
  • BUNGALOW-NO-47
  • BUNGALOW-NO-65
  • BUNGALOW-NO-80
  • BUNGALOW-NO-105
  • BUNGALOW-NO-85
  • BUNGALOW-NO-66
  • BUNGALOW-NO-67
  • BUNGALOW-NO-86
  • BUNGALOW-NO-68
  • BUNGALOW-NO-87
  • BUNGALOW-NO-69
  • BUNGALOW-NO-88
  • BUNGALOW-NO-89
  • BUNGALOW-NO-70
  • BUNGALOW-NO-90
  • BUNGALOW-NO-71
  • BUNGALOW-NO-92
  • BUNGALOW-NO-72
  • BUNGALOW-NO-93
  • BUNGALOW-NO-73
  • BUNGALOW-NO-94
  • BUNGALOW-NO-74
  • BUNGALOW-NO-95
  • BUNGALOW-NO-75
  • BUNGALOW-NO-96
  • BUNGALOW-NO-76
  • BUNGALOW-NO-97
  • BUNGALOW-NO-77
  • BUNGALOW-NO-98
  • BUNGALOW-NO-78
  • BUNGALOW-NO-99
  • BUNGALOW-NO-81
  • BUNGALOW-NO-101
  • BUNGALOW-NO-102
  • BUNGALOW-NO-82
  • BUNGALOW-NO-83
  • BUNGALOW-NO-103
  • BUNGALOW-NO-104
  • BUNGALOW-NO-84
  • BUNGALOW-NO-106
  • BUNGALOW-NO-107
  • BUNGALOW-NO-58
  • BUNGALOW-NO-7
  • BUNGALOW-NO-59
  • BUNGALOW-NO-55
  • BUNGALOW-NO-79
  • BUNGALOW-NO-60
  • BUNGALOW-NO-61
  • BUNGALOW-NO-91
BUNGALOW-NO-3 · Overall Progress 91%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank IDBI BANK
IFSC IBKL0001487
Branch Address 5 WADALA UDYOG BHAVAN NAIGAON WADALA WEST MUMBAI-400031
Country/City