residential Partially Ready To Move Source: rera.mh

Kalpataru Aria RERA Details - P52000050704, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Kalpataru Aria under registration P52000050704 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52000050704
  • Project Name Kalpataru Aria - Phase B
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Raigarh
  • Taluka Karjat
  • Village Varne
  • Original Completion 31 March 2026
  • Revised Completion 31 March 2027
  • Project Area (in Sq.mt.) 3,101.43
  • Total Buildings/Towers 18
  • Documents 6 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 28 April 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 March 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Arena Orchards Private Limited

Promoters, Co-promoters & Members

NameRoleAddress
Devesh BhattDirectorMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Kalpataru Aria - Phase B Row House A1 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House A2 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House A3 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House A4 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House A5 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House A6 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House A7 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House A8 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House A9 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House B19 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House B20 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House B21 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House B22 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House B23 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House B24 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House B25 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House B26 0 0 2 2 2 1 NA
Kalpataru Aria - Phase B Row House B27 0 0 2 2 2 1 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 18
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
Row House 17 units · avg area 140.41 Sq.mt.
Rowe House 1 unit · avg area 139.75 Sq.mt.
  • Row House A1
  • Row House A2
  • Row House A3
  • Row House A4
  • Row House A5
  • Row House A6
  • Row House A7
  • Row House A8
  • Row House A9
  • Row House B19
  • Row House B20
  • Row House B21
  • Row House B22
  • Row House B23
  • Row House B24
  • Row House B25
  • Row House B26
  • Row House B27
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Row House 139.75 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 95.0%
Storm Water Drains 95.0% Landscaping & Tree Planting 95.0% Street Lighting 95.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 65.0% Solid Waste Management And Disposal 50.0%
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 95.0% Aggregate Area Of Recreational Open Space 95.0% Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Row House A1
  • Row House A2
  • Row House A3
  • Row House A4
  • Row House A5
  • Row House A6
  • Row House A7
  • Row House A8
  • Row House A9
  • Row House B19
  • Row House B20
  • Row House B21
  • Row House B22
  • Row House B23
  • Row House B24
  • Row House B25
  • Row House B26
  • Row House B27
Row House A1 · Overall Progress 40%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work10%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work25%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
105 Withdrawal Update Form 1.Pdf
106 Withdrawal Update Form 2.Pdf
107 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0000060
Branch Address Ground Floor Jehangir Building M G Road Fort Mumbai 400023