Nirvaana Residency RERA Details - P52000013902, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Nirvaana Residency under registration P52000013902 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52000013902
  • Project Name Nirvaana Residency Phase-I
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Raigarh
  • Taluka Karjat
  • Village vanjale
  • Original Completion 30 December 2023
  • Revised Completion 31 December 2025
  • Project Area (in Sq.mt.) 5,971.82
  • Total Buildings/Towers 2
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 02 November 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name NIRVAANA CONSTRUCTION CO.

Promoters, Co-promoters & Members

NameRoleAddress
VARDHMAN GANPATLAL SINGHVIPartnerThane, MAHARASHTRA
LALIT CHANDANMAL BOHRAPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Nirvaana Residency Phase-I BUILDING NO 2 WING A AND WING B 0 41 9 0 0 NA
Nirvaana Residency Phase-I BUILDING NO 4 0 11 9 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 40.0% Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 20.0%
Storm Water Drains 20.0% Landscaping & Tree Planting 70.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 20.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Swimming Pool And Club House % not reported Garden 20.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BUILDING NO 2 WING A AND WING B
  • BUILDING NO 4
BUILDING NO 2 WING A AND WING B · Overall Progress 80%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work90%
Sanitary Fittings within the flats / premises
In Progress
% Work50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work60%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BHARAT COOPERATIVE BANK MUMBAI LIMITED
IFSC BCBM0000085
Branch Address Suryamukhi CHSL Bldg No 46 Nehru Nagar Kurla East Mumbai 400024 Maharashtra