Mantra Mirari RERA Details - P52100030037, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Mantra Mirari under registration P52100030037 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100030037
  • Project Name MANTRA MIRARI PHASE 1
  • Project Type Others
  • Project Status Ready to Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Mundhawa
  • Original Completion 30 June 2025
  • Revised Completion 30 June 2025
  • Project Area (in Sq.mt.) 4,924.0
  • Total Buildings/Towers 3
  • Documents 2 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 26 July 2021 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name MANTRA RESIDENCES MUNDHWA PRIVATE LIMITED

Promoters, Co-promoters & Members

NameRoleAddress
ASHISH SATISH GUPTADirectorPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
MANTRA MIRARI PHASE 1 A BUILDING 0 0 23 21 21 84 NA
MANTRA MIRARI PHASE 1 B BUILDING 0 0 23 - 0 101 NA
MANTRA MIRARI PHASE 1 A B COMMERCIAL 0 0 1 - 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 185
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
5 BHK 124 units · avg area 88.21 Sq.mt.
Landowners Unit 51 units · avg area 76.98 Sq.mt.
Shop 10 units · avg area 41.15 Sq.mt.
  • A BUILDING
  • B BUILDING
  • A B COMMERCIAL
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Landowners Unit 76.9 18 0
Landowners Unit 95.34 3 0
3.5 BHK 95.35 39 39
2.5 BHK 76.9 24 24
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 50.0% Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 60.0%
Storm Water Drains 60.0% Landscaping & Tree Planting 20.0% Street Lighting % not reported
Community Buildings 90.0% Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal 90.0%
Water Conservation /Rain Water Harvesting 60.0% Energy Managemcnt 40.0% Fire Protection And Fire Safety Requirements 80.0%
Electrical Meter Room, Sub-station, Receiving Station 20.0% Aggregate Area Of Recreational Open Space % not reported Open Parking 60.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A BUILDING
  • B BUILDING
  • A B COMMERCIAL
A BUILDING · Overall Progress 98%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work80%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0009625
Branch Address Gr Floor Shop no 1 Gera Grand Society Near Vrindawan Garden T P No 438 Pune MH 411037
Country/City