SR Tirupati Nivas RERA Details - P52100034775, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for SR Tirupati Nivas under registration P52100034775 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100034775
  • Project Name TIRUPATI NIVAS
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Kothrud
  • Original Completion 31 May 2024
  • Revised Completion 31 May 2027
  • Project Area (in Sq.mt.) 726.0
  • Total Buildings/Towers 1
  • Documents 16 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 28 April 2022 Expected commencement of civil works and foundation on site.
Original Completion 31 May 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 May 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Others
Individule Name S R CONSTRUCTIONS

Promoters, Co-promoters & Members

NameAddress
SANTOSH ROHIDAS DANGATPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
TIRUPATI NIVAS TIRUPATI NIVAS 0 12 9 9 8 32 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 32
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 16 units · avg area 48.77 Sq.mt.
2 BHK 8 units · avg area 63.84 Sq.mt.
3 BHK 8 units · avg area 85.41 Sq.mt.
  • TIRUPATI NIVAS
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 63.84 8 4
1BHK 54.65 8 1
1BHK 42.9 8 1
3BHK 85.41 8 4
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • TIRUPATI NIVAS
TIRUPATI NIVAS · Overall Progress 58%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work50%
Sanitary Fittings within the flats / premises
In Progress
% Work20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
46 Form 1.Pdf
47 Form 2.Pdf
48 Form 3.Pdf
49 Disclosure Of Sold And Booked Inventory.Pdf
94 Withdrawal Update Form 1.Pdf
95 Withdrawal Update Form 2.Pdf
96 Withdrawal Update Form 3.Pdf
97 Form 2A (FY 2024 2025).Pdf
98 Form 2A (FY 2022 2023).Pdf
99 Form 2A (FY 2023 2024).Pdf
100 Form 5 (FY 2024 2025).Pdf
101 Form 5 (FY 2022 2023).Pdf
102 Form 5 (FY 2023 2024).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank THE COSMOS CO OPERATIVE BANK LIMITED
IFSC COSB0000032
Branch Address SHOP NO 4, 5, KAKDE PLAZA, PHASE II, WARJE, PUNE - 411052
Country/City