- RERA Number PR1170002600803
- Project Name San Petros Residency
- Project Type Residential / Group Housing
- Project Status New Launch
- State Maharashtra
- District Mumbai City
- Taluka Ward GNorth
- Village GNorth-400028
- Original Completion 30 June 2027
- Revised Completion 30 June 2027
- Project Area (in Sq.mt.) 314.38
- Total Buildings/Towers 1
- Documents 5 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
Land, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
| Survey Number 496 | |
Boundary Details |
|
| Boundaries East Final Plot No 495 | Boundaries West Final Plot No 497 |
| Boundaries South Final Plot No 498 and 499 | Boundaries North Existing 9.15 Mtr Wide TP Road |
RERA Coordinates |
|
| Latitude, Longitude 19.015932, 72.8376244 | |
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads & Footpaths % not reported | Water Supply % not reported | Sewerage (Chamber, Lines, Septic Tank , Stp) 10.0% |
| Storm Water Drains % not reported | Landscaping & Tree Planting % not reported | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage And Sullage Water % not reported | Solid Waste Management And Disposal % not reported |
| Water Conservation /Rain Water Harvesting 10.0% | Energy Managemcnt % not reported | Fire Protection And Fire Safety Requirements % not reported |
| Electrical Meter Room, Sub-station, Receiving Station 10.0% | Aggregate Area Of Recreational Open Space % not reported | Open Parking % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | BANK OF BARODA |
|---|---|
| IFSC | BARB0DBDADR |
| Branch Address | JITKAR HOUSE 15 A CADEL ROADNORTH SHIVAJI PARK DADAR MUMBAI MUMBAI MAHARASHTRA 400028 |