Sahasra Serenity RERA Details - PRM/KA/RERA/1251/446/PR/041122/005407 Bangalore

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Sahasra Serenity under registration PRM/KA/RERA/1251/446/PR/041122/005407 in Bangalore, Karnataka. Data is sourced from rera.ka.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PRM/KA/RERA/1251/446/PR/041122/005407
  • Project Name SAHASRA SERENITY
  • Project Type Residential/Group Housing
  • Project Status Ready to Move
  • District Bengaluru Urban
  • Taluka Bengaluru East
  • Original Completion 31 March 2026
  • Documents 66 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 05 October 2022 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2026 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Primary Promoter

SAHASRA BUILDERS
Registered Address No 14, 1st main SBM layout seetha circle, ,BSK 1st stage ,Bengaluru South ,Bengaluru Urban-560050
Location

Land, Address & Location Details

Land parcel, zoning and geo-coordinates as recorded in the project filing.

Address katha no. 595, Sy no. 39/2, Kumbena Agrahara Village, Bidarahalli Hobli , Bangalore East Taluk, Ward No: 54 , Bengaluru East , Bengaluru Urban, Karnataka - 560067

RERA Coordinates

Latitude, Longitude 13.002198, 77.743003
Plans

Plans & Approvals

Statutory approvals obtained or pending against the project site.

Plan Approval No. BBMP/CC/4122/22-23
Authority BBMP - Bruhat Bengaluru Mahanagara Palike
Approved Date 26 July 2022

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Name No. of Basements No. of Slab No. of Slits No. of Open Parking Building Type Height of Tower No. of Floors No. of Units
Sahasra Serenity 1 6 1 150 Residential 14.95 4 125

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units -
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 0 units
3 BHK 0 units
  • Sahasra Serenity
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area No. of Unit
-1 3 BHK 82.64 001
-1 2 BHK 74.14 002
-1 3 BHK 84.12 003
-1 3 BHK 84.22 004
-1 3 BHK 84.22 005
-1 3 BHK 102.24 006
-1 2 BHK 65.81 007
-1 3 BHK 89.7 008
-1 2 BHK 75.4 009
-1 3 BHK 84.22 010
-1 3 BHK 84.22 011
-1 3 BHK 84.3 012
-1 3 BHK 82.11 013
-1 3 BHK 84.22 014
-1 2 BHK 75.31 015
-1 2 BHK 70.11 016
-1 2 BHK 70.42 017
-1 3 BHK 87.42 018
-1 3 BHK 83.05 019
-1 3 BHK 84.72 020
-1 3 BHK 90.61 021
-1 3 BHK 90.61 022
-1 2 BHK 67.43 023
-1 2 BHK 67.5 024
-1 3 BHK 87.69 025
GF 3 BHK 90.78 101
GF 3 BHK 95.96 102
GF 3 BHK 87.69 103
GF 3 BHK 87.79 104
GF 3 BHK 87.79 105
GF 3 BHK 102.24 106
GF 3 BHK 85.51 107
GF 3 BHK 88.6 108
GF 2 BHK 75.4 109
GF 3 BHK 87.96 110
GF 3 BHK 87.79 111
GF 3 BHK 87.87 112
GF 3 BHK 85.68 113
GF 3 BHK 87.8 114
GF 2 BHK 78.88 115
GF 2 BHK 73.68 116
GF 2 BHK 74.01 117
GF 3 BHK 94.64 118
GF 3 BHK 86.64 119
GF 3 BHK 92.66 120
GF 3 BHK 90.61 121
GF 3 BHK 90.61 122
GF 2 BHK 67.43 123
GF 2 BHK 67.5 124
GF 3 BHK 87.69 125
1 3 BHK 90.78 201
1 3 BHK 95.96 202
1 3 BHK 87.69 203
1 3 BHK 87.79 204
1 3 BHK 87.79 205
1 3 BHK 102.24 206
1 3 BHK 85.51 207
1 3 BHK 88.6 208
1 2 BHK 75.4 209
1 3 BHK 87.96 210
1 3 BHK 87.79 211
1 3 BHK 87.87 212
1 3 BHK 85.68 213
1 3 BHK 87.8 214
1 2 BHK 78.88 215
1 2 BHK 73.68 216
1 2 BHK 74.01 217
1 3 BHK 94.64 218
1 3 BHK 86.64 219
1 3 BHK 92.66 220
1 3 BHK 90.61 221
1 3 BHK 90.61 222
1 2 BHK 67.43 223
1 2 BHK 67.5 224
1 3 BHK 87.69 225
2 3 BHK 90.78 301
2 3 BHK 95.96 302
2 3 BHK 87.69 303
2 3 BHK 87.79 304
2 3 BHK 87.79 305
2 3 BHK 102.24 306
2 3 BHK 85.51 307
2 3 BHK 88.6 308
2 2 BHK 75.4 309
2 3 BHK 87.96 310
2 3 BHK 87.79 311
2 3 BHK 87.87 312
2 3 BHK 85.68 313
2 3 BHK 87.8 314
2 2 BHK 78.88 315
2 2 BHK 73.68 316
2 2 BHK 74.01 317
2 3 BHK 94.64 318
2 3 BHK 86.64 319
2 3 BHK 92.66 320
2 3 BHK 90.61 321
2 3 BHK 90.61 322
2 2 BHK 67.43 323
2 2 BHK 67.5 324
2 3 BHK 87.69 325
3 3 BHK 90.78 401
3 3 BHK 95.96 402
3 3 BHK 87.69 403
3 3 BHK 87.79 404
3 3 BHK 87.79 405
3 3 BHK 102.24 406
3 3 BHK 85.51 407
3 3 BHK 88.6 408
3 2 BHK 75.4 409
3 3 BHK 87.96 410
3 3 BHK 87.79 411
3 3 BHK 87.87 412
3 3 BHK 85.68 413
3 3 BHK 87.8 414
3 2 BHK 78.88 415
3 2 BHK 73.68 416
3 2 BHK 74.01 417
3 3 BHK 94.64 418
3 3 BHK 86.64 419
3 3 BHK 92.66 420
3 3 BHK 90.61 421
3 3 BHK 90.61 422
3 2 BHK 67.43 423
3 2 BHK 67.5 424
3 3 BHK 87.69 425
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage - - -
Covered Parking - - -
Open Parking - - -
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Sub Structure Earth Work And Other Leveling Preparation Work % not reported Sub Structure Foundation Footing Work % not reported Sub Structure Upto Plinth Level % not reported
Sub Structure Sub-structure Flooring (Parking Floor, More Than One Floor Below General Ground Level) % not reported Sub Structure Retaining Wall (All Types) % not reported Sup Structure Rcc Or Ms Framed Structure % not reported
Sup Structure Masonry Construction % not reported Sup Structure Plastering Inside , Outside & Ceiling % not reported Sup Structure Joinery: Doors, Windows, Ventilators Etc % not reported
Sup Structure Basic Work Of Water Supply, Sanitary And Electrification % not reported Sup Structure Dadoing, Skirting, Flooring, Tiles Work (All Types) % not reported Sup Structure Railing And Grill Fixing % not reported
Finishing Works Electrification, Water Supply And Sanitary Finishing % not reported Finishing Works Painting % not reported Finishing Works Fire Prevention And Fire Fighting Fitting And Fixture With Network % not reported
Finishing Works Weather Proof Work(tile,concrete) % not reported Finishing Works Wardrobe, Showcase, Kitchen Cabinet, Puja Work % not reported Finishing Works Elevation Work % not reported
Finishing Works Internal And External Work Including Landscapes As Per Sanctioned Drawings % not reported Internal Infrastructure Water Supply % not reported Internal Infrastructure Sewage And Drainage System % not reported
Internal Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported Internal Infrastructure Energy Management % not reported Internal Infrastructure Fire Protection And Fire Safety Requirements % not reported
Internal Infrastructure Solid Waste Management And Disposal % not reported Internal Infrastructure Emergency Evacuation Services % not reported External Infrastructure Water Supply % not reported
External Infrastructure Internal Roads & Footpaths % not reported External Infrastructure Sewage And Drainage System % not reported External Infrastructure Electricity Supply Transformer And Substation % not reported
External Infrastructure Solid Waste Management And Disposal % not reported External Infrastructure Emergency Evacuation Services % not reported External Infrastructure Storm Water Drains % not reported
External Infrastructure Use Of Renewable Energy % not reported External Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported External Infrastructure Fire Protection And Fire Safety Requirements % not reported
External Infrastructure Sewage Treatment Plant (Stp) % not reported External Infrastructure Parks & Tree Planting % not reported External Infrastructure Street Lighting % not reported
Amenities Electricity % not reported Amenities Smart Home Automation % not reported Amenities Cctv Surveillance % not reported
Amenities Club House % not reported Amenities Community Hall % not reported Amenities Outdoor Sports Facility % not reported
Amenities Indoor Sports Facility % not reported Amenities Swimming Pool % not reported Amenities Gym % not reported
Amenities Parks % not reported Amenities Power Backup % not reported Amenities Piped Gas % not reported
Amenities Water And Sanitation % not reported Amenities Air Conditioning % not reported Common Areas Staircases % not reported
Common Areas Lifts % not reported Common Areas Corridor/lobbies % not reported Common Areas Fire Escapes % not reported
Common Areas Common Entrance And Exit For The Building/common Portico/foyer/verandah % not reported Common Areas Basement % not reported Common Areas Terrace % not reported
Common Areas Outer Wall % not reported Common Areas Open Parking Areas % not reported Common Areas Provision For Lodging Of Management Staff And Security Staff % not reported
Common Areas Water Conservation And Renewable Energy % not reported Common Areas Common Storage Spaces % not reported
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Promoter Registration Certificate
Promoter Pan Card
Promoter Address Proof
Affidavit
Fd 1 Balance Sheet 21-22.Pdf
Fd 2 Balance Sheet 20-21.Pdf
Fd 3 Balance Sheet 19-20.Pdf
Fd 4 Profit And Loss 21-22.Pdf
Fd 5 Profit And Loss 20-21.Pdf
Fd 6 Profit And Loss 19-20.Pdf
Fd 7 Not Available.Pdf
Fd 8 Not Available.Pdf
Fd 9 Not Available.Pdf
Fd 10 Not Available.Pdf
Fd 11 Not Available.Pdf
Fd 12 Not Available.Pdf
Fd 13 Not Available.Pdf
Fd 14 Not Available.Pdf
Fd 15 Not Available.Pdf
Fd 16 ITR-V Ack 2021-22.Pdf
Fd 17 ITR-V Ack 2020-21.Pdf
Fd 18 ITR-V Ack.Pdf
Pd 1 Self Attested PAN Card*( Annexure - 66 )
Pd 2 Commencement Certificate*( Annexure - 67 )
Pd 3 Electricity Permission Letter*( Annexure - 68 )
Pd 4 Water Permission Letter*( Annexure - 69 )
Pd 6 Approved Building Plotting Plan*( Annexure - 71 )
Pd 8 Existing Section Plan And Specification( Annexure - 73 )
Pd 9 Sectional Drawing Of The Apartments*( Annexure - 74 )
Pd 10 Project Specifications*( Annexure - 75 )
Pd 11 Approved Section Of Building Infrastructure Plan Of Plotting*( Annexure - 76 )
Pd 12 Area Development Plan Of Project Area*( Annexure - 77 )
Pd 13 Certificate From Registered Engineer Indicating The Structural Safety Of The Building*( Annexure - 78 )
Pd 14 Advocate Search Report*( Annexure - 79 )
Pd 15 Urban Land Ceiling*( Annexure - 80 )
Pd 16 Collaboration Agreement Development Agreement Joint Development Agreement Other Agreement*( Annexure - 81 )
Pd 17 Change Of Land Use*( Annexure - 82 )
Pd 19 Conversion Certificate Under Section 95 Of The KLR Act 1964*( Annexure - 84 )
Pd 20 Any Other Document (Rights Title Interest Name)*( Annexure - 85 )
Pd 21 Proforma Of Agreement For Sale*( Annexure - 86 )
Pd 22 Proforma Of Allotment Letter*( Annexure - 87 )
Pd 24 Brochure*( Annexure - 89 )
Dc 1 Declaration (Form B)*( Annexure - 90 )
Dc 2 Section 3(1) Notarized Affidavit*( Annexure - 91 )
Dc 3 JD AFFIDAVIT CUM DECLARATION*( Annexure - 92 )
Noc 1 ESCOM Electricity*( Annexure - 93 )
Noc 2 KWSSB Water*( Annexure - 94 )
Noc 7 KSPCB( Annexure - 99 )
Photo 1 Project Photo
Od 1 SERENITY GUIDENCE VALUE.Pdf
Od 2 SHARING AGREMENT SERENITY.Pdf
Od 3 SAHASRA GST Certificate.Pdf
Od 4 Registration Certificate - Changed Address.Pdf
Od 5 Village Map.Pdf
Od 6 Title Deed 1970.Pdf
Od 7 GOOGLE MAPS DEMARCATION SERENITY.Pdf
Od 8 STP Design Sahasra Serenity N.Pdf
Od 9 Clarification On Sold And Unsold Units.Pdf
Od 10 BWSSB NOC With Fee Receipt.Pdf
Od 11 Partnership Deed Mc.Pdf
Ld Rtc
Ld Mutation
Ld Encumbrance Certificate
Ld Conversion Order
Ld Sale Deed
Ld Khatha
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank Bank of Baroda
Account Number (RERA) 34960200002737
IFSC BARB0KRPURA
Branch Address K R PURAM Branch
Country/City