VG Boat Club RERA Details - PRM/KA/RERA/1251/310/PR/250822/005192 Bangalore

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for VG Boat Club under registration PRM/KA/RERA/1251/310/PR/250822/005192 in Bangalore, Karnataka. Data is sourced from rera.ka.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PRM/KA/RERA/1251/310/PR/250822/005192
  • Project Name VG BOAT CLUB
  • Project Type Residential/Group Housing
  • Project Status Ready to Move
  • District Bengaluru Urban
  • Taluka Bengaluru South
  • Original Completion 31 December 2025
  • Documents 57 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 14 August 2022 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2025 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Primary Promoter

VINAYAKAIAH BUILDERS AND DEVELOPERS PVT LTD
Registered Address NO 310-A1,75/1,SRI MITRA ESTATES,SANJEEVAPPA ROAD,, NAGAWARA PALYA,10 TH CROSS,CV RAMAN NAGAR ,Bengaluru North ,Bengaluru Urban-560093
Location

Land, Address & Location Details

Land parcel, zoning and geo-coordinates as recorded in the project filing.

Address PID No. SITE/KATHA NO 389/3165/57/2 ,"RAMANASHREE NAGAR", , GOTTIGERE VILLAGE, UTTARAHALLI HOBLI , Bengaluru South , Bengaluru Urban, Karnataka - 560083

RERA Coordinates

Latitude, Longitude 12.865367, 77.597542
Plans

Plans & Approvals

Statutory approvals obtained or pending against the project site.

Plan Approval No. LP NO: BBMP/Addl.Dir/JDSOUTH/0006/22-23
Authority BBMP - Bruhat Bengaluru Mahanagara Palike
Approved Date 01 August 2022

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Name No. of Basements No. of Slab No. of Slits No. of Open Parking Building Type Height of Tower No. of Floors No. of Units
A 1 6 0 10 Residential 15.0 5 10
B 1 6 0 80 Residential 15.0 5 80

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units -
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 0 units
3 BHK 0 units
  • A
  • B
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area No. of Unit
GF 3 BHK 77.82 A001
GF 3 BHK 86.75 A002
1 3 BHK 77.82 A101
1 3 BHK 86.75 A102
2 3 BHK 77.82 A201
2 3 BHK 86.75 A202
3 3 BHK 77.82 A301
3 3 BHK 86.75 A302
4 3 BHK 77.82 A401
4 3 BHK 86.75 A402
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage - - -
Covered Parking - - -
Open Parking - - -
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Common Areas Staircases % not reported Sub Structure Earth Work And Other Leveling Preparation Work % not reported Sub Structure Foundation Footing Work % not reported
Sub Structure Upto Plinth Level % not reported Sub Structure Sub-structure Flooring (Parking Floor, More Than One Floor Below General Ground Level) % not reported Sub Structure Retaining Wall (All Types) % not reported
Sup Structure Rcc Or Ms Framed Structure % not reported Sup Structure Masonry Construction % not reported Sup Structure Plastering Inside , Outside & Ceiling % not reported
Sup Structure Joinery: Doors, Windows, Ventilators Etc % not reported Sup Structure Basic Work Of Water Supply, Sanitary And Electrification % not reported Sup Structure Dadoing, Skirting, Flooring, Tiles Work (All Types) % not reported
Sup Structure Railing And Grill Fixing % not reported Finishing Works Electrification, Water Supply And Sanitary Finishing % not reported Finishing Works Painting % not reported
Finishing Works Fire Prevention And Fire Fighting Fitting And Fixture With Network % not reported Finishing Works Weather Proof Work(tile,concrete) % not reported Finishing Works Wardrobe, Showcase, Kitchen Cabinet, Puja Work % not reported
Finishing Works Elevation Work % not reported Finishing Works Internal And External Work Including Landscapes As Per Sanctioned Drawings % not reported Internal Infrastructure Water Supply % not reported
Internal Infrastructure Sewage And Drainage System % not reported Internal Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported Internal Infrastructure Energy Management % not reported
Internal Infrastructure Fire Protection And Fire Safety Requirements % not reported Internal Infrastructure Solid Waste Management And Disposal % not reported Internal Infrastructure Emergency Evacuation Services % not reported
External Infrastructure Water Supply % not reported External Infrastructure Internal Roads & Footpaths % not reported External Infrastructure Sewage And Drainage System % not reported
External Infrastructure Electricity Supply Transformer And Substation % not reported External Infrastructure Solid Waste Management And Disposal % not reported External Infrastructure Emergency Evacuation Services % not reported
External Infrastructure Storm Water Drains % not reported External Infrastructure Use Of Renewable Energy % not reported External Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported
External Infrastructure Fire Protection And Fire Safety Requirements % not reported External Infrastructure Sewage Treatment Plant (Stp) % not reported External Infrastructure Parks & Tree Planting % not reported
External Infrastructure Street Lighting % not reported Amenities Electricity % not reported Amenities Smart Home Automation % not reported
Amenities Cctv Surveillance % not reported Amenities Club House % not reported Amenities Community Hall % not reported
Amenities Outdoor Sports Facility % not reported Amenities Indoor Sports Facility % not reported Amenities Swimming Pool % not reported
Amenities Gym % not reported Amenities Parks % not reported Amenities Power Backup % not reported
Amenities Piped Gas % not reported Amenities Water And Sanitation % not reported Amenities Air Conditioning % not reported
Common Areas Lifts % not reported Common Areas Corridor/lobbies % not reported Common Areas Fire Escapes % not reported
Common Areas Common Entrance And Exit For The Building/common Portico/foyer/verandah % not reported Common Areas Basement % not reported Common Areas Terrace % not reported
Common Areas Outer Wall % not reported Common Areas Open Parking Areas % not reported Common Areas Provision For Lodging Of Management Staff And Security Staff % not reported
Common Areas Water Conservation And Renewable Energy % not reported Common Areas Common Storage Spaces % not reported
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Promoter Registration Certificate
Promoter Pan Card
Promoter Address Proof
Affidavit
Fd 1 Balance Sheet.Pdf
Fd 2 Balance Sheet FY2020-21.Pdf
Fd 3 Balance Sheet FY2019-20.Pdf
Fd 4 Profit And Loss Statement.Pdf
Fd 5 Profit And Loss FY2020-21.Pdf
Fd 6 Profit And Loss FY2019-20.Pdf
Fd 7 Directors Report.Pdf
Fd 8 Directors Report FY2020-21.Pdf
Fd 9 Directors Report FY2019-20.Pdf
Fd 10 Cash Flow Statement.Pdf
Fd 11 Cash Flow Statememnt FY 20-21.Pdf
Fd 12 Cash Flow Statememnt FY19-20.Pdf
Fd 13 Audit Report.Pdf
Fd 14 Auditros Report FY2020-21.Pdf
Fd 15 Auditros Report FY2019-20.Pdf
Fd 16 ITR V Acknowledgment.Pdf
Fd 17 Acknowledgement FY2020-21.Pdf
Fd 18 Acknowledgemt FY2019-20.Pdf
Pd 1 Self Attested PAN Card*( Annexure - 66 )
Pd 2 Commencement Certificate*( Annexure - 67 )
Pd 3 Electricity Permission Letter*( Annexure - 68 )
Pd 4 Water Permission Letter*( Annexure - 69 )
Pd 5 Approved Layout Plan*( Annexure - 70 )
Pd 6 Approved Building Plotting Plan*( Annexure - 71 )
Pd 7 Existing Layout Plan( Annexure - 72 )
Pd 8 Existing Section Plan And Specification( Annexure - 73 )
Pd 9 Sectional Drawing Of The Apartments*( Annexure - 74 )
Pd 10 Project Specifications*( Annexure - 75 )
Pd 11 Approved Section Of Building Infrastructure Plan Of Plotting*( Annexure - 76 )
Pd 12 Area Development Plan Of Project Area*( Annexure - 77 )
Pd 14 Advocate Search Report*( Annexure - 79 )
Pd 17 Change Of Land Use*( Annexure - 82 )
Pd 21 Proforma Of Agreement For Sale*( Annexure - 86 )
Dc 1 Declaration (Form B)*( Annexure - 90 )
Dc 2 Section 3(1) Notarized Affidavit*( Annexure - 91 )
Dc 3 JD AFFIDAVIT CUM DECLARATION*( Annexure - 92 )
Noc 2 KWSSB Water*( Annexure - 94 )
Noc 7 KSPCB( Annexure - 99 )
Photo 1 Project Photo
Ed 1 13-08-2022
Ed 2 13-08-2022
Ed 3 13-08-2022
Ed 4 13-08-2022
Ed 5 13-08-2022
Ed 6 13-08-2022
Ed 7 13-08-2022
Ed 8 13-08-2022
Ld Rtc
Ld Mutation
Ld Encumbrance Certificate
Ld Conversion Order
Ld Sale Deed
Ld Khatha
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank STATE BANK OF INDIA
Account Number (RERA) 41125616194
IFSC SBIN0014951
Branch Address HULIMAVU