residential Ready to Move Source: rera.mh

Crystal Paradise Residences RERA Details - P51800015472, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Crystal Paradise Residences under registration P51800015472 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800015472
  • Project Name CRYSTAL PARADISE RESIDENCES
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Andheri
  • Village Andheri
  • Original Completion 30 June 2024
  • Revised Completion 24 November 2024
  • Project Area (in Sq.mt.) 1,547.14
  • Total Buildings/Towers 1
  • Documents 18 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 27 February 2018 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 24 November 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Others
Individule Name Prithvi Sthapti LLP

Promoters, Co-promoters & Members

NameRoleAddress
JATIN YOGESH MEHTAPartnerz3zNKTHrCVVq4qBf1AlQ1k552PZ6od2O994ifaigpe7TV/Gc3rMEZyrvrz/gORuY, Palghar, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
CRYSTAL PARADISE RESIDENCES Crystal Paradise Residences 0 40 10 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 74
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 26 units · avg area 37.67 Sq.mt.
2 BHK 48 units · avg area 54.01 Sq.mt.
  • Crystal Paradise Residences
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 53.57 8 8
2BHK 53.69 8 8
2BHK 53.78 8 8
2BHK 53.63 8 7
1BHK 37.83 9 8
2BHK 55.43 9 7
2BHK 53.72 7 6
1BHK 36.44 8 8
1BHK 38.61 9 9
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Community Buildings % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Crystal Paradise Residences
Crystal Paradise Residences · Overall Progress 72%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work80%
Sanitary Fittings within the flats / premises
In Progress
% Work80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work50%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 AD 5CR Amended Drawing Building Layout Compressed.Pdf.Pdf
2 AD 5CR Amended Plan Approval.Pdf.Pdf
3 LAYOUT.Pdf.Pdf
4 IOD.Pdf.Pdf
5 Drawing 1.Pdf.Pdf
6 Drawing 2.Pdf.Pdf
7 Drawing 3.Pdf.Pdf
8 PAN ARENA DEVELOPERS.Pdf.Pdf
9 Tile Report.Pdf.Pdf
10 Declaration Form B.Pdf.Pdf
11 MahaRERA Title Report.Pdf.Pdf
12 Form B Prithvi Sthapti LLP.Pdf.Pdf
13 Form B Declaration.Pdf.Pdf
14 PROFORMA SALE AGREEMENT.Pdf.Pdf
15 Crystal Paradise Draft AFS.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank INDIAN BANK
IFSC IDIB000S010
Branch Address Mangal Ashirwad Ground floor S V Road Santacruz West Mumbai
Country/City