- RERA Number P51900002869
- Project Name OMKAR TOWER
- Project Type Residential
- Project Status Ready to Move
- State MAHARASHTRA
- District Mumbai City
- Taluka Ward ABCD
- Village ABCD-400004
- Original Completion 31 December 2018
- Revised Completion 31 December 2019
- Project Area (in Sq.mt.) 542.64
- Total Buildings/Towers 1
- Documents 42 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role |
|---|---|
| KUMARPAL PHOOLCHAND GANDHI | Authorized Signatory |
| BHARATKUMAR PHOOLCHAND GANDHI | Partner |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Basements | No. of Plinth | No. of Podium | No. of Slab | No. of Slits | No. of Open Parking | No. of Closed Parking |
|---|---|---|---|---|---|---|---|---|---|
| OMKAR TOWER | OMKAR TOWER | 2019-12-31 | 0 | 1 | 0 | 20 | 0 | 0 | 0 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- OMKAR TOWER
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| SHOP1 | 19.82 | 1 | 1 |
| SHOP 2 | 19.04 | 1 | 1 |
| SHOP 3 | 14.81 | 1 | 1 |
| SHOP 4 | 16.41 | 1 | 1 |
| SHOP 5 | 26.90 | 1 | 1 |
| SHOP 6 | 10.42 | 1 | 1 |
| SHOP 7 | 8.42 | 1 | 1 |
| SHOP 8 | 1.75 | 1 | 0 |
| OFFICE 1 | 101 | 1 | 1 |
| OFFICE 2 | 14.17 | 1 | 1 |
| 1BHK | 23.60 | 1 | 1 |
| 2BHK | 48.87 | 1 | 1 |
| 1BHK | 24.82 | 1 | 1 |
| 1BHK | 22.46 | 1 | 1 |
| 3BHK | 65.76 | 1 | 1 |
| 1BHK | 35.88 | 1 | 1 |
| 1BHK | 24.18 | 1 | 1 |
| 1BHK | 25.62 | 1 | 1 |
| 1BHK | 22.40 | 1 | 1 |
| 1BHK | 35.74 | 1 | 1 |
| 1BHK | 24.58 | 1 | 1 |
| 1BHK | 24.30 | 1 | 1 |
| 1BHK | 25.45 | 1 | 1 |
| 1BHK | 22.21 | 1 | 1 |
| 1BHK | 24.15 | 1 | 1 |
| 1BHK | 25.61 | 1 | 1 |
| 1BHK | 22.52 | 1 | 1 |
| 2BHK | 54.15 | 1 | 1 |
| 2BHK | 46.75 | 1 | 1 |
| 2BHK | 53.47 | 1 | 1 |
| 1BHK | 37.19 | 1 | 1 |
| 3BHK | 108 | 1 | 1 |
| 2BHK | 53.48 | 1 | 1 |
| 2BHK | 49 | 1 | 1 |
| 3BHK | 107.13 | 1 | 1 |
| 2BHK | 52.90 | 1 | 1 |
| 2BHK | 53.32 | 1 | 1 |
| 2BHK | 52.84 | 1 | 1 |
| 2BHK | 53.45 | 1 | 1 |
| 3BHK | 107.66 | 1 | 1 |
| 2BHK | 59.06 | 1 | 1 |
| 1BHK | 24.87 | 2 | 2 |
| 2BHK | 52.72 | 2 | 2 |
| 2BHK | 52.73 | 2 | 2 |
| 1BHK | 23.45 | 4 | 4 |
| 1BHK | 39.47 | 11 | 9 |
| OFFICE 3 | 24.55 | 1 | 1 |
| OFFICE 4 | 5.49 | 1 | 1 |
| OFFICE 5 | 5.34 | 1 | 1 |
| OFFICE 6 | 5.44 | 1 | 1 |
| OFFICE 7 | 5.51 | 1 | 0 |
| OFFICE 8 | 3.91 | 1 | 1 |
| OFFICE 9 | 39.27 | 1 | 0 |
| OFFICE 10 | 23.49 | 1 | 0 |
| OFFICE 11 | 24.44 | 1 | 1 |
| OFFICE 12 | 47.76 | 1 | 1 |
| OFFICE 13 | 39.48 | 1 | 0 |
| OFFICE 14 | 39.32 | 4 | 0 |
| 2BHK | 44.60 | 1 | 1 |
| 1BHK | 24.21 | 1 | 1 |
| 1BHK | 37.17 | 10 | 8 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 28 | 23 | 10 |
| Covered Parking | 0 | 0 | 0 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths % not reported | Water Conservation Rainwater Harvesting % not reported | Energy Management % not reported |
| Fire Protection And Fire Safety Requirements 40% | Electrical Meter Room Substation Receivingstation 85% | Aggregate Area Of Recreational Open Space % not reported |
| Open Parking % not reported | Water Supply 85% | Sewerage 90% |
| Storm Water Drains 75% | Landscaping Tree Planting % not reported | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal 70% |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- OMKAR TOWER
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | UNION BANK OF INDIA |
|---|---|
| IFSC | UBIN0535222 |