residential Under Construction Source: rera.mh

Goyal Fairmont RERA Details - P51800056119, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Goyal Fairmont under registration P51800056119 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800056119
  • Project Name LOURDES CHSL
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Borivali
  • Village Eksar
  • Original Completion 30 June 2026
  • Revised Completion 30 June 2026
  • Project Area (in Sq.mt.) 600.99
  • Total Buildings/Towers 1
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 11 May 2024 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Society
Individule Name LOURDES CHSL

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
LOURDES CHSL GOYAL FAIRMONT 0 11 3 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 10
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 1 unit · avg area 52.35 Sq.mt.
1RK 1 unit · avg area 18.86 Sq.mt.
Shop 7 units · avg area 18.17 Sq.mt.
Office space 1 unit · avg area 208.77 Sq.mt.
  • GOYAL FAIRMONT
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 17.72 1 0
1BHK 52.35 1 0
Shop 25.29 1 0
Shop 13.6 1 0
Shop 16.13 1 1
Shop 19.59 1 1
Office space 208.77 1 1
1RK 18.86 1 0
Shop 16.38 1 1
Shop 18.5 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 20.0% Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal 30.0%
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • GOYAL FAIRMONT
GOYAL FAIRMONT · Overall Progress 36%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0001232
Branch Address P T OFFICIALS CHS LTD BHUVNEHWARI RAM NAGAR SAI BABA NAGAR BORIVALI WEST MUMBAI 400092