Kumar Urban KUL Palladio RERA Details - P51800012150, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Kumar Urban KUL Palladio under registration P51800012150 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800012150
  • Project Name AEROVISTA
  • Project Type Others
  • Project Status Ready to Move
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Andheri
  • Village Andheri
  • Original Completion 30 December 2023
  • Revised Completion 28 December 2025
  • Project Area (in Sq.mt.) 3,672.94
  • Total Buildings/Towers 3
  • Documents 35 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 01 September 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 28 December 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Gagangiri Construction

Promoters, Co-promoters & Members

NameRoleAddress
Harsh Rajendra DewoolkarPartnerMumbai Suburban, MAHARASHTRA
Jitendra Govind DewoolkarPartnerMumbai Suburban, MAHARASHTRA
Anita Jitendra DewoolkarPartnerMumbai Suburban, MAHARASHTRA
Parth Jitendra DewoolkarPartnerMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
AEROVISTA Kul Palladio 0 121 16 0 0 0 NA
AEROVISTA Sahar Tower CHSL - - 16 2 Common Basement + Stilt + 13 Residential Floor 13 46 A
AEROVISTA Sahar Tower CHSL - - 16 2 Common Basement + Stilt + 13 Residential Floor 13 49 B

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 95
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 44 units · avg area 39.51 Sq.mt.
2 BHK 47 units · avg area 54.78 Sq.mt.
Shop 4 units · avg area 107.02 Sq.mt.
  • Kul Palladio
  • Sahar Tower CHSL
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 80.86 1 0
Shop 99.44 1 0
Shop 115.71 1 0
2BHK 53.9 3 1
1BHK 34.39 17 17
1BHK 44.61 1 1
Shop 132.06 1 0
1BHK 39.96 5 4
2BHK 59.29 4 3
1BHK 49.72 4 3
2BHK 57.16 10 4
2BHK 55.76 8 1
1BHK 46.0 6 6
2BHK 55.3 8 3
1BHK 39.5 11 11
2BHK 51.12 14 5
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 80.0% Water Supply 85.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 90.0%
Storm Water Drains 90.0% Landscaping & Tree Planting % not reported Street Lighting 50.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 80.0% Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 90.0%
Electrical Meter Room, Sub-station, Receiving Station 90.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Kul Palladio
  • Sahar Tower CHSL
  • Sahar Tower CHSL
Kul Palladio · Overall Progress 89%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work85%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 Sahar Mhada Noc Dated04 09 2020 .Pdf.Pdf
2 Revised IOD Letter 11112020.Pdf.Pdf
3 Sahar Tower Demarcation Plan (00000003) MHADA 11zon.Pdf.Pdf
4 Sahar Tower IOA Pages 1 3.Pdf.Pdf
5 Sahar Tower IOA Pages 4 Plan No 1 11zon.Pdf.Pdf
6 Sahar Tower IOA Pages 5 Plan No.Pdf.Pdf
7 Sahar Tower IOA Pages 6 Plan.Pdf.Pdf
8 Sahar Tower IOA Pages 7 Plan 4.Pdf.Pdf
9 Sahar Tower IOA Pages 8 Plan No.Pdf.Pdf
10 Sahar Tower IOA Pages 9 Plan No.Pdf.Pdf
11 Sahar Tower IOA Pages 10 11zon.Pdf.Pdf
12 Sahar Tower IOA Pages 11 8 11zon.Pdf.Pdf
13 Sahar Tower IOA Pages 12 9 11zon.Pdf.Pdf
14 Sahar Tower IOA Pages 13 10 11zon.Pdf.Pdf
15 Sahar Tower IOA Pages 14 11 11zon.Pdf.Pdf
16 Sahar Project Approved IOD Dated 5th June 2014.Pdf.Pdf
17 Sahar Further CC 13042023.Pdf.Pdf
18 Part OC 19102023.Pdf.Pdf
19 KBMRPL.Pdf.Pdf
20 Gagangiri Construction PAN.Pdf.Pdf
21 Letter To 153 Pantnagar CHSL For Induction Of Members Palladio.Pdf.Pdf
22 GVK Mumbai AAI Permission 13th Floor Sahar.Pdf.Pdf
23 DA Index 2 3 10.Pdf.Pdf
24 Resolution Of The Association Of Allotees.Pdf.Pdf
25 Aerovista Bar Chart For Extention.Pdf.Pdf
26 Kul Palladio Form B.Pdf.Pdf
27 TITLE CERTIFICATE OF SAHAR TOWER CHS LTD.Pdf.Pdf
28 Sahar Tower Title Report.Pdf.Pdf
29 Declaration Form B 11zon.Pdf.Pdf
30 Form B Declaration.Pdf.Pdf
31 KUL Palladio Undertaking NEW.Pdf.Pdf
32 Draft AFS.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0001225
Branch Address VEERA DESAI ROAD, ANDHERI WEST, MUMBAI-400053
Country/City