Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Nobles Empire Solitaire RERA Details - P51900004114, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Nobles Empire Solitaire under registration P51900004114 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51900004114
  • Project Name EMPIRE SOLITAIRE
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Mumbai City
  • Taluka Mumbai City
  • Village Mumbai City
  • Original Completion 31 December 2018
  • Revised Completion 31 December 2024
  • Project Area (in Sq.mt.) 1,001.11
  • Total Buildings/Towers 1
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 08 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2018 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name AALAY DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
TASNEEM ASGAR GANDHIPartnerMumbai City, MAHARASHTRA
MANOOR ASGARALI PATANWALAPartnerPune, MAHARASHTRA
ABBAS ASGARALI PATANWALAPartnerPune, MAHARASHTRA
HUSEIN ASGAR GANDHIPartnerMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
EMPIRE SOLITAIRE EMPIRE SOLITAIRE B WING 46 0 28 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 36
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 7 units · avg area 36.35 Sq.mt.
2 BHK 27 units · avg area 75.94 Sq.mt.
3 BHK 2 units · avg area 119.67 Sq.mt.
  • EMPIRE SOLITAIRE B WING
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 30.78 1 0
3BHK 125.22 1 1
3BHK 114.13 1 1
1BHK 30.74 3 3
1BHK 43.82 3 3
2BHK 75.34 12 11
2BHK 76.42 15 15
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 85.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • EMPIRE SOLITAIRE B WING
EMPIRE SOLITAIRE B WING · Overall Progress 95%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work95%
Sanitary Fittings within the flats / premises
In Progress
% Work85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work75%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0000143
Branch Address CRAWFORD MARKET MUMBAI
Country/City