Pride Park Royale RERA Details - P51800053602, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Pride Park Royale under registration P51800053602 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800053602
  • Project Name Park Royale Phase III
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Andheri
  • Village Marol
  • Original Completion 31 December 2026
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 1,449.33
  • Total Buildings/Towers 2
  • Documents 54 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 10 November 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Others
Individule Name Shivranjani Properties LLP

Promoters, Co-promoters & Members

NameAddress
Sanjay Baboo JainMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Park Royale Phase III E Wing 0 102 26 0 0 NA
Park Royale Phase III F Wing 0 102 26 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 164
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 80 units · avg area 76.62 Sq.mt.
3 BHK 84 units · avg area 103.23 Sq.mt.
  • E Wing
  • F Wing
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 72.26 1 0
3BHK 94.48 1 0
3BHK 87.44 1 0
2BHK 69.47 1 0
2BHK 78.8 18 9
3BHK 105.82 20 1
3BHK 98.73 20 6
2BHK 76.59 20 13
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 40.0%
Storm Water Drains 75.0% Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 55.0% Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 30.0%
Electrical Meter Room, Sub-station, Receiving Station 25.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • E Wing
  • F Wing
E Wing · Overall Progress 62%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work76%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work50%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work10%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Layout Plan.Pdf.Pdf
2 Building Plan Approval 1.Pdf.Pdf
3 Building Plan Approval 2.Pdf.Pdf
4 Building Plan Approval 3.Pdf.Pdf
5 Building Plan Approval 4.Pdf.Pdf
6 Building Plan Approval 5.Pdf.Pdf
7 Building Plan Approval 7.Pdf.Pdf
8 Building Plan Approval 8.Pdf.Pdf
9 Building Plan Approval 9.Pdf.Pdf
10 Building Plan Approval 12.Pdf.Pdf
11 Building Plan Approval 15.Pdf.Pdf
12 Building Plan Approval 16.Pdf.Pdf
13 Building Plan Approval 21.Pdf.Pdf
14 Building Plan Approval 22.Pdf.Pdf
15 0219 ISSUE Drawing 2 1 11zon.Pdf.Pdf
16 0219 ISSUE Drawing 3 2 11zon.Pdf.Pdf
17 0219 ISSUE Drawing 4 3 11zon.Pdf.Pdf
18 0219 ISSUE Drawing 2.Pdf.Pdf
19 0219 ISSUE Drawing 3.Pdf.Pdf
20 0219 ISSUE Drawing 4.Pdf.Pdf
21 0219 ISSUE Drawing 5.Pdf.Pdf
22 0219 ISSUE Drawing 6.Pdf.Pdf
23 0219 ISSUE Drawing 7.Pdf.Pdf
24 0219 ISSUE Drawing 8.Pdf.Pdf
25 0219 ISSUE Drawing 9.Pdf.Pdf
26 0219 ISSUE Drawing 10.Pdf.Pdf
27 0219 ISSUE Drawing 11.Pdf.Pdf
28 0219 ISSUE Drawing 12.Pdf.Pdf
29 0219 ISSUE Drawing 13.Pdf.Pdf
30 0219 ISSUE Drawing 14.Pdf.Pdf
31 0219 ISSUE Drawing 15.Pdf.Pdf
32 0219 ISSUE Drawing 16.Pdf.Pdf
33 0219 ISSUE Drawing 17.Pdf.Pdf
34 0219 ISSUE Drawing 18.Pdf.Pdf
35 0219 ISSUE Drawing 19.Pdf.Pdf
36 0219 ISSUE Drawing 20.Pdf.Pdf
37 0219 ISSUE Drawing 21.Pdf.Pdf
38 0219 ISSUE Drawing 22.Pdf.Pdf
39 0219 ISSUE Drawing 23.Pdf.Pdf
40 0219 ISSUE Drawing 24.Pdf.Pdf
41 Pan Card.Pdf.Pdf
42 Consent.Pdf.Pdf
43 Development Agreement 1.Pdf.Pdf
44 Development Agreement 2.Pdf.Pdf
45 Conveyance Deed.Pdf.Pdf
46 Form B Affidavit Cum Declaration.Pdf.Pdf
47 Legal Title 124 125 Final.Pdf.Pdf
48 Legal Title 126 Final.Pdf.Pdf
49 Sample Allotment Letter.Pdf.Pdf
50 Devation Of Allotment Letter.Pdf.Pdf
51 Sale Agreement.Pdf.Pdf
52 Deviation Report.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0000012
Branch Address 386, Veer Savarkar Marg, opp Siddhivinayak Temple, Prabhadevi, Mumbai - 400025
Country/City