Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Under Construction Source: rera.mh

Raheja Park West RERA Details - P51800034035, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Raheja Park West under registration P51800034035 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800034035
  • Project Name RAHEJA PARK WEST
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Andheri
  • Village Andheri
  • Original Completion 31 December 2026
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 3,784.38
  • Total Buildings/Towers 1
  • Documents 17 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 17 March 2022 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name GOKUL DEVELOPERS

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
RAHEJA PARK WEST RAHEJA PARK WEST 0 219 18 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 78
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
3 BHK 52 units · avg area 121.39 Sq.mt.
4 BHK 26 units · avg area 160.93 Sq.mt.
  • RAHEJA PARK WEST
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
3 BHK B2 115.53 13 1
3 BHK A2 114.13 13 0
3 BHK B1 127.38 13 1
4 BHK B 160.93 13 0
4 BHK A 160.93 13 0
3 BHK A1 128.51 13 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 60.0%
Storm Water Drains % not reported Landscaping & Tree Planting 50.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 90.0%
Electrical Meter Room, Sub-station, Receiving Station 50.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • RAHEJA PARK WEST
RAHEJA PARK WEST · Overall Progress 86%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work75%
Sanitary Fittings within the flats / premises
In Progress
% Work5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work80%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 Building Plan Approval NA Order For Plotted Development (1).Pdf.Pdf
2 1 Copy Of Layout Approval (In Case Of Layout) (4).Pdf.Pdf
3 2 Copy Of Layout Approval (In Case Of Layout) (1).Pdf.Pdf
4 3 Copy Of Layout Approval (In Case Of Layout).Pdf.Pdf
5 PLAN.Pdf.Pdf
6 Plan II.Pdf.Pdf
7 PLAN III.Pdf.Pdf
8 2378752Amendletter Signed.Pdf.Pdf
9 FORM 2A 2024 2025.Pdf.Pdf
10 1 PAN Card (3).Pdf.Pdf
11 1 Copy Of The Legal Title Report (13).Pdf.Pdf
12 Rera Affidavit Form B.Pdf.Pdf
13 Title Certificate 2022.Pdf.Pdf
14 2 Proforma Of The Allotment Letter And Agreement For Sale (2).Pdf.Pdf
15 Agreement For Sale 2022.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0000004
Branch Address NARIMAN POINT
Country/City