Shree Sainath Towers RERA Details - P51800011710, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Shree Sainath Towers under registration P51800011710 in Mumbai, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800011710
  • Project Name Tilak Nagar Shree Sainath CHS Ltd
  • Project Type Others
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Mumbai Suburban
  • Taluka Kurla
  • Village Kurla
  • Original Completion 31 July 2018
  • Revised Completion 31 July 2018
  • Project Area (in Sq.mt.) 1,394.65
  • Total Buildings/Towers 1
  • Documents 15 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 31 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 July 2018 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 July 2018 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Sankalp Developers
Other Description NA

Promoters, Co-promoters & Members

NameRole
Dinesh Babulal SalechaPartner
Amratlal Devichand JainAuthorized Signatory
Amratlal Devichand JainPartner
Dinesh Laxmichand SanghviPartner
Vinodkumar Himatlal JainPartner
Lalitkumar Tolchand ToganiPartner
Mukesh Hastimal MuthaliyaPartner
Bhavesh Champaklal JainPartner
Dinesh Bhabumal SalechaPartner

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
Tilak Nagar Shree Sainath CHS Ltd Tilak Nagar Shree Sainath CHS Ltd 0 1 0 15 1 21 1

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 75
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 1 unit · avg area 1.00 Sq.mt.
2 BHK 62 units · avg area 58.14 Sq.mt.
COMMERCIAL 12 units · avg area 13.83 Sq.mt.
  • Tilak Nagar Shree Sainath CHS Ltd
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 58.55 2 0
2BHK 59.48 4 0
2BHK 55.76 1 0
1 1 1 1
2 BHK 58.55 27 25
2BHK 59.48 14 10
2BHK 55.76 14 13
COMMERCIAL 8.83 1 1
COMMERCIAL 9.94 1 0
COMMERCIAL 10.22 1 1
COMMERCIAL 12.45 1 1
COMMERCIAL 13.66 1 1
COMMERCIAL 13.75 1 1
COMMERCIAL 14.22 5 3
COMMERCIAL 26.02 1 1
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 10 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Conservation Rainwater Harvesting % not reported Energy Management % not reported
Fire Protection And Fire Safety Requirements 95% Electrical Meter Room Substation Receivingstation 95% Aggregate Area Of Recreational Open Space % not reported
Open Parking % not reported Water Supply 95% Sewerage 95%
Storm Water Drains 95% Landscaping Tree Planting 100% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal 100%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Tilak Nagar Shree Sainath CHS Ltd
Tilak Nagar Shree Sainath CHS Ltd · Overall Progress 90%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Complete
% Work100%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Complete
% Work100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work95%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
1 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration In FORM B
1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
1 Proforma Of Allotment Letter
1 Other
2 Other
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK
IFSC ICIC0000348
Country/City