Trimurti Balaji Empire RERA Details - P51800005019, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Trimurti Balaji Empire under registration P51800005019 in Mumbai, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800005019
  • Project Name BALAJI EMPIRE
  • Project Type Others
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Mumbai Suburban
  • Taluka Kurla
  • Village Kurla
  • Original Completion 31 December 2008
  • Revised Completion 30 December 2022
  • Project Area (in Sq.mt.) 2,011
  • Total Buildings/Towers 1
  • Documents 13 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2008 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2022 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Others
Individule Name M/S TRIMURTI & K. MUKESH BUILDERS AND DEVELOPERS
Experience Details
Project NameAddressLand AreaType of ProjectBuild Plot CountApartment countProject End Date
NOT APPLICABLENOT APPLICABLE0Others002017-07-17
Other Description a Joint Venture business entity

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
BALAJI EMPIRE BALAJI EMPIRE 0 1 0 7 1 15 1

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 108
Configurations 5
Inventory Type RESIDENTIAL
Configuration Distribution
1 RK 48 units · avg area 25.30 Sq.mt.
1 BHK 12 units · avg area 39.30 Sq.mt.
2 BHK 19 units · avg area 63.45 Sq.mt.
3 BHK 7 units · avg area 87.60 Sq.mt.
SHOP 22 units · avg area 21.24 Sq.mt.
  • BALAJI EMPIRE
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1 RK 25.3 48 48
1BHK 39.30 12 8
2BHK 63.45 19 12
3BHK 87.60 7 5
SHOP 16.5 16 16
SHOP 39.9 1 1
SHOP 33.55 1 1
SHOP 20.05 1 1
SHOP 36.65 2 2
SHOP 36.5 1 1
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 6 0 60
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Conservation Rainwater Harvesting % not reported Energy Management % not reported
Fire Protection And Fire Safety Requirements 60% Electrical Meter Room Substation Receivingstation 60% Aggregate Area Of Recreational Open Space 60%
Open Parking 60% Water Supply 60% Sewerage 60%
Storm Water Drains 60% Landscaping Tree Planting 100% Street Lighting 100%
Community Buildings 60% Treatment And Disposal Of Sewage Sullage Water 60% Solid Waste Management Disposal % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BALAJI EMPIRE
BALAJI EMPIRE · Overall Progress 66%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
In Progress
% Work80%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work60%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work60%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
In Progress
% Work60%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work40%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work60%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
1 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration In FORM B
1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
1 Proforma Of Allotment Letter
2 Proforma Of Allotment Letter
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank SVC COOPERATIVE BANK LTD
IFSC SVCB0000024
Country/City