EV 9 Square RERA Details - P51700055650, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for EV 9 Square under registration P51700055650 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700055650
  • Project Name EV 9 Square
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Navi Mumbai (M Corp.)
  • Original Completion 31 December 2028
  • Revised Completion 31 December 2028
  • Project Area (in Sq.mt.) 5,330.04
  • Total Buildings/Towers 1
  • Documents 59 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 05 April 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name EV HOMES CONSTRUCTIONS PVT LTD
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
SAFFIRE HEIGHTSPLOT NO 32A AND 33A SECTOR 12 KALAMBOLI TALUKA PANVEL DISTT RAGIAD 4102091800CompletedResidential / Group Housing1702010-03-312012-05-24NoNA
E V CASTLEPLOT NO 110 SECTOR 9 ULVE TALUKA PANVEL DISTT RAIGAD 410206848.75CompletedResidential / Group Housing1262016-04-302016-04-27NoNA
SINAI TOWERKAKINAD KOCHI KERALA 6820171514CompletedResidential / Group Housing1382017-07-312017-02-03NoNA
ZION I AND IIPLOT NO 29 AND 30 SECTOR 25 NERUL EAST NAVI MUMBAI 4007063178CompletedResidential / Group Housing2592016-03-312017-05-26NoNA

Promoters, Co-promoters & Members

NameRoleAddress
ELENJIKAMALIL VARKEY THOMASManaging DirectorThane, MAHARASHTRA
JOISE THOMASManaging DirectorThane, MAHARASHTRA
VICKY THOMASManaging DirectorThane, MAHARASHTRA
RICKI THOMASManaging DirectorThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
EV 9 Square Sale/Incentive - EV 9 Square 0 293 29 29 29 144 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 144
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
3 BHK 115 units · avg area 74.84 Sq.mt.
Shop 19 units · avg area 35.15 Sq.mt.
Reserved for NMMC 2 units · avg area 66.93 Sq.mt.
Reserved for CIDCO 8 units · avg area 66.93 Sq.mt.
  • Sale/Incentive - EV 9 Square
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 43.55 1 1
Shop 52.0 2 2
3BHK 66.93 39 3
Reserved for NMMC 66.93 2 0
Shop 24.9 3 0
Shop 39.06 2 2
Shop 39.65 1 1
Shop 39.81 2 2
Reserved for CIDCO 66.93 8 0
Shop 27.94 2 0
Shop 39.01 1 1
Shop 24.65 3 3
Shop 39.0 1 1
Shop 40.3 1 1
3BHK 79.39 19 9
3BHK 83.74 19 4
3BHK 75.14 19 1
3BHK 77.35 19 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Sale/Incentive - EV 9 Square
Sale/Incentive - EV 9 Square · Overall Progress 52%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work20.5%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work16.5%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work36%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 3 Copy Of The Legal Title Report.Pdf
5 1 A Details Of Encumbrances Concerned To Finance.Pdf
6 2 A Details Of Encumbrances Concerned To Finance.Pdf
7 1 B Details Of Encumbrances Concerned To Legal.Pdf
8 2 B Details Of Encumbrances Concerned To Legal.Pdf
9 1 Copy Of Layout Approval (In Case Of Layout).Pdf
10 1 Building Plan Approval NA Order For Plotted Development.Pdf
11 2 Building Plan Approval NA Order For Plotted Development.Pdf
12 3 Building Plan Approval NA Order For Plotted Development.Pdf
13 4 Building Plan Approval NA Order For Plotted Development.Pdf
14 5 Building Plan Approval NA Order For Plotted Development.Pdf
15 6 Building Plan Approval NA Order For Plotted Development.Pdf
16 7 Building Plan Approval NA Order For Plotted Development.Pdf
17 8 Building Plan Approval NA Order For Plotted Development.Pdf
18 9 Building Plan Approval NA Order For Plotted Development.Pdf
19 10 Building Plan Approval NA Order For Plotted Development.Pdf
20 11 Building Plan Approval NA Order For Plotted Development.Pdf
21 1 Commencement Certificates NA Order For Plotted Development.Pdf
22 1 Declaration About Commencement Certificate.Pdf
23 1 Declaration In FORM B.Pdf
24 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
25 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
26 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
27 1 CERSAI Details.Pdf
28 1 Disclosure Of Sold Booked Inventory.Pdf
29 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
30 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
31 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
32 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
33 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
34 3 Disclosure Of Interest In Other Real Estate Organizations.Pdf
35 4 Disclosure Of Interest In Other Real Estate Organizations.Pdf
36 1 Proforma Of Allotment Letter.Pdf
37 1 Proforma Of Agreement For Sale.Pdf
38 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
39 1 Deviation Report With Respect To Allotment Letter.Pdf
40 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
41 1 Other – Technical.Pdf
42 2 Other – Technical.Pdf
43 3 Other – Technical.Pdf
44 4 Other – Technical.Pdf
45 5 Other – Technical.Pdf
46 6 Other – Technical.Pdf
47 7 Other – Technical.Pdf
55 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
63 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
67 Form 1.Pdf
68 Form 2.Pdf
69 Form 3.Pdf
70 Disclosure Of Sold And Booked Inventory.Pdf
71 Withdrawal Update Form 1.Pdf
73 Withdrawal Update Form 2.Pdf
75 Withdrawal Update Form 3.Pdf
77 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Branch Address Near Avlon School,Sector 19B, Navi Mumbai - 400703
Country/City