Galaxy Maplewoods RERA Details - P51700050973, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Galaxy Maplewoods under registration P51700050973 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700050973
  • Project Name MAPLEWOODS PHASE 1
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 31 December 2028
  • Revised Completion 31 December 2028
  • Project Area (in Sq.mt.) 20,000.0
  • Total Buildings/Towers 2
  • Documents 74 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 16 May 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name M/S BKS Galaxy Realtors LLP
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Galaxy NebulaSector 10 Kharghar Navi Mumbai2650.06CompletedResidential / Group Housing2802013-06-302012-07-12NoNA
Galaxy OrionSector 35D Kharghar2699.55CompletedResidential / Group Housing2932013-12-312013-07-07NoNA
Galaxy CarinaSector 15 Kharghar2781.79CompletedIndustrial1892015-12-312015-05-21NoNA
GreenwoodsSector - 35E Kharghar6549.57CompletedIndustrial21962023-12-312023-12-31NoNA
Sai Proviso AashleshaSector 4A Koparkhairane4076.54CompletedIndustrial21042019-12-312019-06-04NoNA
Sai Proviso CountyVillage Shirdhone Tal Panvel20949.94CompletedResidential / Group Housing194162023-06-302023-06-30NoNA

Promoters, Co-promoters & Members

NameRoleAddress
Siddhant Sanjay GawandePartnerThane, MAHARASHTRA
Brij Achruram GuptaPartnerThane, MAHARASHTRA
Kashish Brij GuptaPartnerThane, MAHARASHTRA
Kulbir Dayal Singh RekhiPartnerMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
MAPLEWOODS PHASE 1 Building D 28 191 44 0 0 NA
MAPLEWOODS PHASE 1 Building F 28 204 34 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Swimming Pool % not reported Society Office % not reported Gymnasium % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Building D
  • Building F
Building D · Overall Progress 33%
Excavation
Complete
% Work100%
Basement (if any)
In Progress
% Work85%
Podiums (if any)
Not Started
% Work0%
Plinth
In Progress
% Work85%
Stilt Floor
In Progress
% Work70%
Slabs of Super Structure
In Progress
% Work28%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 3 Copy Of The Legal Title Report.Pdf
5 4 Copy Of The Legal Title Report.Pdf
6 1 A Details Of Encumbrances Concerned To Finance.Pdf
7 2 A Details Of Encumbrances Concerned To Finance.Pdf
8 3 A Details Of Encumbrances Concerned To Finance.Pdf
9 1 B Details Of Encumbrances Concerned To Legal.Pdf
10 2 B Details Of Encumbrances Concerned To Legal.Pdf
11 3 B Details Of Encumbrances Concerned To Legal.Pdf
12 1 Copy Of Layout Approval (In Case Of Layout).Pdf
13 1 Building Plan Approval NA Order For Plotted Development.Pdf
14 2 Building Plan Approval NA Order For Plotted Development.Pdf
15 3 Building Plan Approval NA Order For Plotted Development.Pdf
16 4 Building Plan Approval NA Order For Plotted Development.Pdf
17 5 Building Plan Approval NA Order For Plotted Development.Pdf
18 6 Building Plan Approval NA Order For Plotted Development.Pdf
19 7 Building Plan Approval NA Order For Plotted Development.Pdf
20 8 Building Plan Approval NA Order For Plotted Development.Pdf
21 9 Building Plan Approval NA Order For Plotted Development.Pdf
22 10 Building Plan Approval NA Order For Plotted Development.Pdf
23 11 Building Plan Approval NA Order For Plotted Development.Pdf
24 12 Building Plan Approval NA Order For Plotted Development.Pdf
25 13 Building Plan Approval NA Order For Plotted Development.Pdf
26 14 Building Plan Approval NA Order For Plotted Development.Pdf
27 15 Building Plan Approval NA Order For Plotted Development.Pdf
28 16 Building Plan Approval NA Order For Plotted Development.Pdf
29 17 Building Plan Approval NA Order For Plotted Development.Pdf
30 18 Building Plan Approval NA Order For Plotted Development.Pdf
31 19 Building Plan Approval NA Order For Plotted Development.Pdf
32 20 Building Plan Approval NA Order For Plotted Development.Pdf
33 1 Commencement Certificates NA Order For Plotted Development.Pdf
34 1 Declaration About Commencement Certificate.Pdf
35 1 Declaration In FORM B.Pdf
36 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
37 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
38 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
39 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
40 5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
41 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
42 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
43 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
44 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
45 5 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
46 1 Disclosure Of Sold Booked Inventory.Pdf
47 1 CERSAI Details.Pdf
48 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
49 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
50 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
51 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
52 5 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
53 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
54 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
55 3 Disclosure Of Interest In Other Real Estate Organizations.Pdf
56 4 Disclosure Of Interest In Other Real Estate Organizations.Pdf
57 5 Disclosure Of Interest In Other Real Estate Organizations.Pdf
58 1 Proforma Of Allotment Letter.Pdf
59 1 Proforma Of Agreement For Sale.Pdf
60 2 Proforma Of Agreement For Sale.Pdf
61 3 Proforma Of Agreement For Sale.Pdf
62 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
63 1 Deviation Report With Respect To Allotment Letter.Pdf
64 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
65 1 Other – Legal.Pdf
66 2 Other – Legal.Pdf
88 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
89 Form 1.Pdf
90 Form 2.Pdf
91 Form 3.Pdf
92 Disclosure Of Sold And Booked Inventory.Pdf
105 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.