View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Nirvana Utsav Residency under registration PM1271012500213 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PM1271012500213
  • Project Name Utsav Residency Building No. 1 A and B
  • Project Type Mixed
  • Project Status Under Construction
  • State Maharashtra
  • District Raigarh
  • Taluka Panvel
  • Village Dhansar
  • Original Completion 31 March 2028
  • Revised Completion 31 March 2028
  • Project Area (in Sq.mt.) 4,700.0
  • Total Buildings/Towers 1
  • Documents 2 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 04 July 2025 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 March 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Nirvana Realty

Promoters, Co-promoters & Members

NameRoleAddress
Jinesh Bipin PatelPartnerMumbai City, MAHARASHTRA
Vipul Karsan PatelPartnerMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Utsav Residency Building No. 1 A and B Nirvana Building 01 12 20 8 8 8 73 A
Utsav Residency Building No. 1 A and B Nirvana Building 01 12 20 8 8 7 77 B

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Energy Managemcnt % not reported Internal Roads & Footpaths % not reported Water Supply % not reported
Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported Storm Water Drains % not reported Landscaping & Tree Planting % not reported
Street Lighting % not reported Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported
Solid Waste Management And Disposal % not reported Water Conservation /Rain Water Harvesting % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Nirvana Building 01
  • Nirvana Building 01
Nirvana Building 01 · Overall Progress 22%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0000228
Branch Address ICICI Bank Ltd., Vyapar Bhavan, H001, Apmc Market, Market 2, Phase 2, Dana Bazaar, Navi Mumbai.400703
Country/City