Pushpam Balibaug Rekreasi RERA Details - P52000077037, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Pushpam Balibaug Rekreasi under registration P52000077037 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52000077037
  • Project Name BALIBAUG REKREASI
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Raigarh
  • Taluka Alibag
  • Village Kawir
  • Original Completion 31 December 2025
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 907.0
  • Total Buildings/Towers 1
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 16 July 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Pushpam Infra LLP

Promoters, Co-promoters & Members

NameRoleAddress
Shrikant Ashok ChopdaPartnerPune, MAHARASHTRA
Ashok Dagduram ChopdaPartnerPune, MAHARASHTRA
Sachin Ashok ChopdaPartnerPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
BALIBAUG REKREASI Building A 14 0 4 4 0 14 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 14
Configurations 1
Inventory Type COMMERCIAL
Configuration Distribution
Studio Apartment 14 units · avg area 38.42 Sq.mt.
  • Building A
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Studio Apartment 37.62 6 0
Studio Apartment 38.39 2 0
Studio Apartment 39.7 2 0
Studio Apartment 39.0 4 2
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Building A
Building A · Overall Progress 44%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work30%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BANK OF MAHARASHTRA
IFSC MAHB0000003
Branch Address Pawar Bldg 1257, Deccan Gymkhana,, Shivajinagar, Pune 411004
Country/City