Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Qualcon Palms RERA Details - P52000015616, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Qualcon Palms under registration P52000015616 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52000015616
  • Project Name QUALCON PALMS
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Raigarh
  • Taluka Panvel
  • Village Karade Kh.
  • Original Completion 01 May 2023
  • Revised Completion 01 May 2023
  • Project Area (in Sq.mt.) 7,390.0
  • Total Buildings/Towers 7
  • Documents 2 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 15 March 2018 Expected commencement of civil works and foundation on site.
Original Completion 01 May 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 01 May 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Qualcon Ecostar Realty LLP

Promoters, Co-promoters & Members

NameRoleAddress
Kavita Deepak MehtaPartnerRaigarh, MAHARASHTRA
Pooja Manish MehtaPartnerRaigarh, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
QUALCON PALMS Building no - 1 0 0 6 0 0 NA
QUALCON PALMS Building No - 2 0 0 6 0 0 NA
QUALCON PALMS Building No - 3 0 0 6 0 0 NA
QUALCON PALMS Building No - 4 0 0 6 0 0 NA
QUALCON PALMS Building No - 5 0 0 6 0 0 NA
QUALCON PALMS Building No - 6 0 0 6 0 0 NA
QUALCON PALMS Building No - 7 0 0 6 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 296
Configurations 8
Inventory Type RESIDENTIAL
Configuration Distribution
1 RK 57 units · avg area 28.73 Sq.mt.
1 RK B wing 28 units · avg area 28.70 Sq.mt.
1 RK C wing 14 units · avg area 28.70 Sq.mt.
1 RK A wing 18 units · avg area 28.74 Sq.mt.
Habitable Room 79 units · avg area 19.47 Sq.mt.
Habitable Room Cwing 15 units · avg area 19.51 Sq.mt.
Habitable Room Bwing 38 units · avg area 19.43 Sq.mt.
Habitable Room Awing 47 units · avg area 19.51 Sq.mt.
  • Building no - 1
  • Building No - 2
  • Building No - 3
  • Building No - 4
  • Building No - 5
  • Building No - 6
  • Building No - 7
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1 RK 27.25 3 3
Habitable Room 19.21 5 4
1 RK 27.44 6 6
Habitable Room 19.51 5 5
1 RK 30.19 2 2
1 RK 30.37 6 6
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Building no - 1
  • Building No - 2
  • Building No - 3
  • Building No - 4
  • Building No - 5
  • Building No - 6
  • Building No - 7
Building no - 1 · Overall Progress 25%
Excavation
Complete
% Work100%
Basement (if any)
In Progress
% Work90%
Podiums (if any)
Not Started
% Work0%
Plinth
In Progress
% Work90%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank DCB BANK LIMITED
IFSC DCBL0000084
Branch Address 7-8, NEEL UDYAN, SANJAY CO OP SOCIETY SECTOR 03E KALAMBOLI NAVI MUMBAI
Country/City