Shanmukhi Bilvam RERA Details - PR1271012500964, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Shanmukhi Bilvam under registration PR1271012500964 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PR1271012500964
  • Project Name Shanmukhi Bilvam
  • Project Type Residential / Group Housing
  • Project Status New Launch
  • State Maharashtra
  • District Raigarh
  • Taluka Panvel
  • Village Shedung
  • Original Completion 31 March 2029
  • Revised Completion 31 March 2029
  • Project Area (in Sq.mt.) 3,960.0
  • Total Buildings/Towers 1
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 25 September 2025 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2029 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 March 2029 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Shanmukhi Infra

Promoters, Co-promoters & Members

NameRoleAddress
Dheeraj Ramesh KapoorPARTNERRaigarh, MAHARASHTRA
Ravindra Krishna ReddyPARTNERRaigarh, MAHARASHTRA
Shekhar ReddyPARTNERRaigarh, MAHARASHTRA
Venkat Laxman ReddyPARTNERRaigarh, MAHARASHTRA
Santosh Arjun SinghPARTNERThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Shanmukhi Bilvam Wing A and Wing B 44 16 8 8 7 63 Wing A
Shanmukhi Bilvam Wing A and Wing B 44 16 8 8 7 40 Wing B

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Community Buildings % not reported Internal Roads & Footpaths % not reported Water Supply % not reported
Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported Storm Water Drains % not reported Landscaping & Tree Planting % not reported
Street Lighting % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Wing A and Wing B
  • Wing A and Wing B
Wing A and Wing B · Overall Progress 64%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
In Progress
% Work75%
Slabs of Super Structure
In Progress
% Work75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work45%
Sanitary Fittings within the flats / premises
In Progress
% Work45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work45%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
10 Form 2A (FY 2025 2026).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0000334
Branch Address ICICI Bank Ltd., Plot No. 5, Panvel Matheran Road, Sector 19, New Panvel, Navi Mumbai.410206