residential Ready to Move Source: rera.mh

Tirupati Pulin Co Op Housing Society Ltd RERA Details - P51700006582, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Tirupati Pulin Co Op Housing Society Ltd under registration P51700006582 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700006582
  • Project Name PULIN CO-OP HOUSING SOCIETY LTD
  • Project Type Others
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Navi Mumbai (M Corp.)
  • Original Completion 30 December 2031
  • Revised Completion 30 December 2031
  • Project Area (in Sq.mt.) 1,445.0
  • Total Buildings/Towers 2
  • Documents 43 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 14 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2031 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2031 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name TIRUPATI DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
MANILAL PALAN GOSARPartnerMumbai Suburban, MAHARASHTRA
SHEELA RAMNIKLAL GOSARPartnerThane, MAHARASHTRA
PULIN JAYANT PARIKHPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
PULIN CO-OP HOUSING SOCIETY LTD PULIN TOWER 18 1 9 0 0 NA
PULIN CO-OP HOUSING SOCIETY LTD PULIN TOWER 18 1 2 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 78
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
OFFICES ON 1ST FLOOR 4 units · avg area 68.90 Sq.mt.
2 BHK 30 units · avg area 49.93 Sq.mt.
3 BHK 28 units · avg area 73.00 Sq.mt.
SHOP 16 units · avg area 20.50 Sq.mt.
  • PULIN TOWER
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
3BHK 73.0 14 8
2BHK 51.0 14 8
2BHK MINI 35.0 1 1
SHOP 20.5 8 8
OFFICES ON 1ST FLOOR 68.9 2 2
3BHK 73.0 14 8
2BHK 51.0 14 8
2BHK MINI 35.0 1 1
SHOP 20.5 8 8
OFFICES ON 1ST FLOOR 68.9 2 2
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • PULIN TOWER
  • PULIN TOWER
PULIN TOWER · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval (IOD).Pdf
6 1 Commencement Certificates NA Order For Plotted Development.Pdf
7 1 Declaration In FORM B.Pdf
8 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
9 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
10 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
11 3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
12 4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
13 5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
14 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
15 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
16 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
17 1 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
18 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
19 1 Certificates Of CA (Form 3).Pdf
20 2 Certificates Of CA (Form 3).Pdf
21 3 Certificates Of CA (Form 3).Pdf
22 4 Certificates Of CA (Form 3).Pdf
23 5 Certificates Of CA (Form 3).Pdf
24 6 Certificates Of CA (Form 3).Pdf
25 1 Certificates Of CA (Form 5).Pdf
26 2 Certificates Of CA (Form 5).Pdf
27 3 Certificates Of CA (Form 5).Pdf
28 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
29 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
30 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
31 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
32 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
33 1 Proforma Of Allotment Letter.Pdf
34 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
35 1 Status Of Formation Of Legal Entity (Society Co Op Etc.).Pdf
42 Form 1.Pdf
43 Form 2.Pdf
44 Form 3.Pdf
45 Disclosure Of Sold And Booked Inventory.Pdf
58 Form 2A (FY 2024 2025).Pdf
59 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank STATE BANK OF INDIA
IFSC SBIN0060347
Branch Address APMC, GROMA MARKET BR, SECTOR 19, CENTRAL FACILITY PHASE II, MARKET II, VASHI, NAVI MUMBAI
Country/City