Tulip Kingdom RERA Details - PM1270002500625, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Tulip Kingdom under registration PM1270002500625 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PM1270002500625
  • Project Name Tulip Kingdom
  • Project Type Mixed
  • Project Status Under Construction
  • State Maharashtra
  • District Raigarh
  • Taluka Panvel
  • Village Wahal
  • Original Completion 31 December 2028
  • Revised Completion 31 December 2028
  • Project Area (in Sq.mt.) 3,099.33
  • Total Buildings/Towers 1
  • Documents 2 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 21 August 2025 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Proprietor
Individule Name Shivam Enterprises Proprietor Prakash M Nakrani, Krushna N Kadu, Gajanan G Naik, Shantaram G Naik, Chandrakan B Naik, Narhari D Naik, 7.Mehul J Mistry

Promoters, Co-promoters & Members

NameRoleAddress
Prakash Manubhai NakraniIndividualThane, MAHARASHTRA
Krushna Narayan KaduIndividualRaigarh, MAHARASHTRA
Gajanan Gana NaikIndividualRaigarh, MAHARASHTRA
Shantaram Gana NaikIndividualRaigarh, MAHARASHTRA
Chandrakan Balaram NaikIndividualRaigarh, MAHARASHTRA
Narhari Dharma NaikIndividualRaigarh, MAHARASHTRA
Mehul Jagdish MistryIndividualMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Tulip Kingdom Tulip Kingdom 38 199 14 14 14 160 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Fire Protection And Fire Safety Requirements % not reported Internal Roads & Footpaths % not reported Water Supply % not reported
Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported Storm Water Drains % not reported Landscaping & Tree Planting % not reported
Street Lighting % not reported Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported
Solid Waste Management And Disposal % not reported Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Tulip Kingdom
Tulip Kingdom · Overall Progress 11%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank G P PARSIK BANK
IFSC PJSB0000042
Branch Address C QUEEN EXCELLANCY SHOP NO 1,2,3, SECTOR 44 A, PLOT NO 63,64,65 AND 73,74,75 OFF PALM BEACH ROAD NEAR SEAWOOD STATION KARAVE NERUL WEST NAVI MUMBAI 400706