View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Ved Poojan Palacia under registration P52000018360 in Navi Mumbai, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52000018360
  • Project Name POOJAN PALACIA A AND B WING
  • Project Type Residential
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Raigarh
  • Taluka Karjat
  • Village Dahiwali T. Waredi
  • Original Completion 30 May 2023
  • Project Area (in Sq.mt.) 1,706
  • Total Buildings/Towers 3
  • Documents 40 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 26 October 2018 Expected commencement of civil works and foundation on site.
Original Completion 30 May 2023 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individual Name VED DEVELOPERS
Other Description NA

Promoters, Co-promoters & Members

NameRole
ALPESH BHAILAL PATELAuthorized Signatory
ALPESH AMBALAL PATELPartner
PINALBEN ALPESH PATELPartner
GEETA ALPESH PATELPartner
Location

Land, Address & Location Details

Land parcel, zoning and geo-coordinates as recorded in the project filing.

Survey Number 162/A/1 AND 2

Boundary Details

Boundaries East 162 HNO 1 Boundaries West 98 GUNTHA PLOT
Boundaries South WAHAL VILLAGE Boundaries North 159 GUNTHA PLOT

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
POOJAN PALACIA A AND B WING POOJAN PALACIA A WING 2020-05-31 0 1 0 5 1 7 1
POOJAN PALACIA A AND B WING POOJAN PALACIA B WING 2022-05-31 0 0 0 0 0 0 0
POOJAN PALACIA A AND B WING POOJAN PALACIA E WING 2022-05-31 0 0 0 0 0 0 0

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 77
Configurations 15
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 20 units · avg area 26.37 Sq.mt.
SHOP1 1 unit · avg area 14.01 Sq.mt.
2 BHK 12 units · avg area 38.75 Sq.mt.
SHOP2 1 unit · avg area 10.25 Sq.mt.
SHOP3 1 unit · avg area 26.35 Sq.mt.
SHOP4 1 unit · avg area 14.30 Sq.mt.
SHOP5 1 unit · avg area 21.84 Sq.mt.
SHOP6 1 unit · avg area 14.30 Sq.mt.
SHOP7 1 unit · avg area 11.44 Sq.mt.
SHOP8 1 unit · avg area 15.08 Sq.mt.
SHOP9 1 unit · avg area 14.30 Sq.mt.
SHOP10 1 unit · avg area 14.30 Sq.mt.
SHOP11 1 unit · avg area 10.72 Sq.mt.
BHK 28 units · avg area 26.60 Sq.mt.
SHOP 6 units · avg area 13.20 Sq.mt.
  • POOJAN PALACIA A WING
  • POOJAN PALACIA B WING
  • POOJAN PALACIA E WING
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
SHOP9 14.30 1 0
SHOP10 14.30 1 0
SHOP11 10.72 1 0
2BHK 38.04 8 0
1BHK 25.38 8 0
SHOP1 14.01 1 0
SHOP2 10.25 1 0
SHOP3 26.35 1 0
SHOP4 14.30 1 0
SHOP5 21.84 1 0
SHOP6 14.30 1 0
SHOP7 11.44 1 0
SHOP8 15.08 1 0
1BHK 26.15 4 0
1BHK 27.47 8 0
2BHK 40.16 4 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 10 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Conservation Rainwater Harvesting % not reported Energy Management % not reported
Fire Protection And Fire Safety Requirements % not reported Electrical Meter Room Substation Receivingstation % not reported Aggregate Area Of Recreational Open Space % not reported
Open Parking 7% Water Supply % not reported Sewerage % not reported
Storm Water Drains % not reported Landscaping Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • POOJAN PALACIA A WING
  • POOJAN PALACIA B WING
  • POOJAN PALACIA E WING
POOJAN PALACIA A WING · Overall Progress 20%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
In Progress
% Work1%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
Not Started
% Work0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Not Started
% Work0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Not Started
% Work0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Not Started
% Work0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
1 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration In FORM B
1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
4 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
6 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
7 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
8 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
9 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
1 Disclosure Of Sold/ Booked Inventory
2 Disclosure Of Sold/ Booked Inventory
1 Annual Audit Report Of Statutory CA (Form 5)
2 Annual Audit Report Of Statutory CA (Form 5)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018-19)
2 Annual Audit Report Of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020-21)
1 Proforma Of Allotment Letter
1 Occupancy Certificate/ Completion Certificate/ Architect'S Certificate Of Completion For Plotted Development
1 Status Of Formation Of Legal Entity (Society/Co Op Etc.)
2 Status Of Formation Of Legal Entity (Society/Co Op Etc.)
3 Status Of Formation Of Legal Entity (Society/Co Op Etc.)
1 Other
2 Other
3 Other
4 Other
5 Other
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ANDHRA BANK
IFSC ANDB0001530