RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number PRM/KA/RERA/1251/309/PR/200622/005015
- Project Name V-REGALIAA
- Project Type Residential/Group Housing
- Project Status Ready to Move
- District Bengaluru Urban
- Taluka Bengaluru North
- Original Completion 30 September 2024
- Documents 78 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Primary Promoter
ADARSH INFRALand, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
| Address SY NO. 64 & 55, KHATHA NO. 17/64 , HORAMAVU VILLAGE, K R PURAM HOBLI , Bengaluru North , Bengaluru Urban, Karnataka - 560043 |
RERA Coordinates |
|
| Latitude, Longitude 13.0259, 77.6625 | |
Plans & Approvals
Statutory approvals obtained or pending against the project site.
| Plan Approval No. | BBMP/AD.COM/MDP/0459/21-22 |
|---|---|
| Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| Approved Date | 27 December 2021 |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Name | No. of Basements | No. of Slab | No. of Slits | No. of Open Parking | Building Type | Height of Tower | No. of Floors | No. of Units |
|---|---|---|---|---|---|---|---|---|
| V-REGALIAA | 0 | 4 | 1 | 92 | Residential | 14.95 | 3 | 83 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- V-REGALIAA
| Floor | Apartment Type | Carpet Area | No. of Unit |
|---|---|---|---|
| -1 | 2 BHK | 64.46 | G-1 |
| -1 | 3 BHK | 80.53 | G-2 |
| -1 | 3 BHK | 82.66 | G-3 |
| -1 | 2 BHK | 57.73 | G-4 |
| -1 | 3 BHK | 82.73 | G-5 |
| -1 | 2 BHK | 57.83 | G-6 |
| -1 | 2 BHK | 53.26 | G-7 |
| -1 | 2 BHK | 74.05 | G-8 |
| -1 | 2 BHK | 71.41 | G-9 |
| -1 | 2 BHK | 69.24 | G-10 |
| -1 | 3 BHK | 82.68 | G-12 |
| -1 | 3 BHK | 82.98 | G-13 |
| -1 | 2 BHK | 77.72 | G-14 |
| -1 | 3 BHK | 81.12 | G-15 |
| -1 | 2 BHK | 62.01 | G-16 |
| -1 | 2 BHK | 67.43 | G-17 |
| -1 | 3 BHK | 93.23 | G-18 |
| -1 | 2 BHK | 68.54 | G-19 |
| -1 | 3 BHK | 86.83 | G-20 |
| -1 | 3 BHK | 80.67 | G-21 |
| GF | 2 BHK | 64.46 | 101 |
| GF | 3 BHK | 80.53 | 102 |
| GF | 3 BHK | 83.59 | 103 |
| GF | 2 BHK | 57.73 | 104 |
| GF | 3 BHK | 83.66 | 105 |
| GF | 2 BHK | 57.83 | 106 |
| GF | 3 BHK | 83.57 | 107 |
| GF | 2 BHK | 74.05 | 108 |
| GF | 3 BHK | 96.30 | 109 |
| GF | 2 BHK | 69.24 | 110 |
| GF | 3 BHK | 96.47 | 111 |
| GF | 3 BHK | 83.61 | 112 |
| GF | 3 BHK | 83.57 | 113 |
| GF | 2 BHK | 77.72 | 114 |
| GF | 3 BHK | 81.13 | 115 |
| GF | 2 BHK | 62.01 | 116 |
| GF | 2 BHK | 67.43 | 117 |
| GF | 3 BHK | 93.23 | 118 |
| GF | 2 BHK | 68.54 | 119 |
| GF | 3 BHK | 86.83 | 120 |
| GF | 3 BHK | 81.13 | 121 |
| 1 | 2 BHK | 64.46 | 201 |
| 1 | 3 BHK | 80.53 | 202 |
| 1 | 3 BHK | 83.59 | 203 |
| 1 | 2 BHK | 57.73 | 204 |
| 1 | 3 BHK | 83.66 | 205 |
| 1 | 2 BHK | 57.83 | 206 |
| 1 | 3 BHK | 83.57 | 207 |
| 1 | 2 BHK | 74.05 | 208 |
| 1 | 3 BHK | 96.30 | 209 |
| 1 | 2 BHK | 69.24 | 210 |
| 1 | 3 BHK | 96.47 | 211 |
| 1 | 3 BHK | 83.61 | 212 |
| 1 | 3 BHK | 83.57 | 213 |
| 1 | 2 BHK | 77.72 | 214 |
| 1 | 3 BHK | 81.13 | 215 |
| 1 | 2 BHK | 62.01 | 216 |
| 1 | 2 BHK | 67.43 | 217 |
| 1 | 3 BHK | 93.23 | 218 |
| 1 | 2 BHK | 68.54 | 219 |
| 1 | 3 BHK | 86.83 | 220 |
| 1 | 3 BHK | 81.13 | 221 |
| 2 | 2 BHK | 64.46 | 301 |
| 2 | 3 BHK | 80.53 | 302 |
| 2 | 3 BHK | 83.59 | 303 |
| 2 | 2 BHK | 57.73 | 304 |
| 2 | 3 BHK | 83.66 | 305 |
| 2 | 2 BHK | 57.83 | 306 |
| 2 | 3 BHK | 83.57 | 307 |
| 2 | 2 BHK | 74.05 | 308 |
| 2 | 3 BHK | 96.30 | 309 |
| 2 | 2 BHK | 69.24 | 310 |
| 2 | 3 BHK | 96.47 | 311 |
| 2 | 3 BHK | 83.61 | 312 |
| 2 | 3 BHK | 83.57 | 313 |
| 2 | 2 BHK | 77.72 | 314 |
| 2 | 3 BHK | 81.13 | 315 |
| 2 | 2 BHK | 62.01 | 316 |
| 2 | 2 BHK | 67.43 | 317 |
| 2 | 3 BHK | 93.23 | 318 |
| 2 | 2 BHK | 68.54 | 319 |
| 2 | 3 BHK | 86.83 | 320 |
| 2 | 3 BHK | 81.13 | 321 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | - | - | - |
| Covered Parking | - | - | - |
| Open Parking | - | - | - |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Sub Structure Earth Work And Other Leveling Preparation Work % not reported | Sub Structure Foundation Footing Work % not reported | Sub Structure Upto Plinth Level % not reported |
| Sub Structure Sub-structure Flooring (Parking Floor, More Than One Floor Below General Ground Level) % not reported | Sub Structure Retaining Wall (All Types) % not reported | Sup Structure Rcc Or Ms Framed Structure % not reported |
| Sup Structure Masonry Construction % not reported | Sup Structure Plastering Inside , Outside & Ceiling % not reported | Sup Structure Joinery: Doors, Windows, Ventilators Etc % not reported |
| Sup Structure Basic Work Of Water Supply, Sanitary And Electrification % not reported | Sup Structure Dadoing, Skirting, Flooring, Tiles Work (All Types) % not reported | Sup Structure Railing And Grill Fixing % not reported |
| Finishing Works Electrification, Water Supply And Sanitary Finishing % not reported | Finishing Works Painting % not reported | Finishing Works Fire Prevention And Fire Fighting Fitting And Fixture With Network % not reported |
| Finishing Works Weather Proof Work(tile,concrete) % not reported | Finishing Works Wardrobe, Showcase, Kitchen Cabinet, Puja Work % not reported | Finishing Works Elevation Work % not reported |
| Finishing Works Internal And External Work Including Landscapes As Per Sanctioned Drawings % not reported | Internal Infrastructure Water Supply % not reported | Internal Infrastructure Sewage And Drainage System % not reported |
| Internal Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported | Internal Infrastructure Energy Management % not reported | Internal Infrastructure Fire Protection And Fire Safety Requirements % not reported |
| Internal Infrastructure Solid Waste Management And Disposal % not reported | Internal Infrastructure Emergency Evacuation Services % not reported | Internal Infrastructure Electricity Supply Transformer And Substation % not reported |
| Internal Infrastructure Sewage Treatment Plant (Stp) % not reported | External Infrastructure Water Supply % not reported | External Infrastructure Internal Roads & Footpaths % not reported |
| External Infrastructure Sewage And Drainage System % not reported | External Infrastructure Electricity Supply Transformer And Substation % not reported | External Infrastructure Solid Waste Management And Disposal % not reported |
| External Infrastructure Emergency Evacuation Services % not reported | External Infrastructure Storm Water Drains % not reported | External Infrastructure Use Of Renewable Energy % not reported |
| External Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported | External Infrastructure Fire Protection And Fire Safety Requirements % not reported | External Infrastructure Sewage Treatment Plant (Stp) % not reported |
| External Infrastructure Parks & Tree Planting % not reported | External Infrastructure Street Lighting % not reported | Amenities Electricity % not reported |
| Amenities Smart Home Automation % not reported | Amenities Cctv Surveillance % not reported | Amenities Club House % not reported |
| Amenities Community Hall % not reported | Amenities Outdoor Sports Facility % not reported | Amenities Indoor Sports Facility % not reported |
| Amenities Swimming Pool % not reported | Amenities Gym % not reported | Amenities Parks % not reported |
| Amenities Power Backup % not reported | Amenities Piped Gas % not reported | Amenities Water And Sanitation % not reported |
| Amenities Air Conditioning % not reported | Amenities Multipurpose Hall % not reported | Amenities Children Play Areas % not reported |
| Amenities Swimming Pool & Deck Area % not reported | Common Areas Staircases % not reported | Common Areas Lifts % not reported |
| Common Areas Corridor/lobbies % not reported | Common Areas Fire Escapes % not reported | Common Areas Common Entrance And Exit For The Building/common Portico/foyer/verandah % not reported |
| Common Areas Basement % not reported | Common Areas Terrace % not reported | Common Areas Outer Wall % not reported |
| Common Areas Open Parking Areas % not reported | Common Areas Provision For Lodging Of Management Staff And Security Staff % not reported | Common Areas Water Conservation And Renewable Energy % not reported |
| Common Areas Common Storage Spaces % not reported | Common Areas Stilt Floor % not reported |
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | IDFC FIRST BANK |
|---|---|
| Account Number (RERA) | 10090663977 |
| IFSC | IDFB0080168 |
| Branch Address | FRAZER TOWN |