Bold Aspire RERA Details - PRM/KA/RERA/1250/304/PR/210924/007058 Bangalore

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Bold Aspire under registration PRM/KA/RERA/1250/304/PR/210924/007058 in Bangalore, Karnataka. Data is sourced from rera.ka.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PRM/KA/RERA/1250/304/PR/210924/007058
  • Project Name Bold Aspire
  • Project Type Residential/Group Housing
  • Project Status Under Construction
  • District Bengaluru Rural
  • Taluka Hosakote
  • Original Completion 31 December 2026
  • Documents 94 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 05 July 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2026 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Primary Promoter

Bold Developers
Registered Address 2nd Floor, Site No.4/1,,K.R Puram Hobli, Pattandura Agrahara, Whitefield Main Road ,Bengaluru East ,Bengaluru Urban-560066
Location

Land, Address & Location Details

Land parcel, zoning and geo-coordinates as recorded in the project filing.

Address Survey no 9/2,9/3,9/4,9/5, Harohalli Main road , Thimmandahalli Village, Near Whitefield Iskcon temple,Whitefield , Hosakote , Bengaluru Rural, Karnataka - 560087

RERA Coordinates

Latitude, Longitude 12.956597280902606, 77.7740164929237
Plans

Plans & Approvals

Statutory approvals obtained or pending against the project site.

Plan Approval No. CC/03/2024-25
Authority Local Planing Authority
Approved Date 04 July 2024

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Name No. of Basements No. of Slab No. of Slits No. of Open Parking Building Type Height of Tower No. of Floors No. of Units
Aspire 0 5 1 178 Residential 14.95 4 162

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units -
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 0 units
3 BHK 0 units
  • Aspire
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area No. of Unit
GF 3 BHK 85.91880342 101
GF 2 BHK 63.66499443 102
GF 3 BHK 85.91044221 103
GF 3 BHK 89.33017466 104
GF 2 BHK 76.17985879 105
GF 3 BHK 89.33017466 106
GF 3 BHK 83.29988852 107
GF 3 BHK 83.29988852 108
GF 3 BHK 83.29988852 109
GF 2 BHK 70.22017837 110
GF 2 BHK 70.22017837 111
GF 3 BHK 83.29988852 112
GF 3 BHK 83.29988852 113
GF 3 BHK 83.29988852 114
GF 3 BHK 83.29988852 115
GF 3 BHK 108.1103679 116
GF 3 BHK 106.1603493 117
GF 3 BHK 106.1603493 118
GF 3 BHK 108.1103679 119
GF 3 BHK 85.91044221 120
GF 2 BHK 63.66499443 121
GF 2 BHK 63.66499443 122
GF 2 BHK 63.66499443 123
GF 2 BHK 76.17985879 124
GF 3 BHK 89.33017466 125
GF 3 BHK 89.33017466 126
GF 3 BHK 106.1603493 127
GF 2 BHK 63.66499443 128
GF 2 BHK 63.66499443 129
GF 2 BHK 63.66499443 130
GF 2 BHK 63.66499443 131
GF 2 BHK 76.17985879 132
GF 3 BHK 89.33017466 133
GF 3 BHK 89.33017466 134
GF 3 BHK 106.1603493 135
GF 3 BHK 106.1603493 136
GF 3 BHK 85.91044221 137
GF 3 BHK 85.91044221 138
GF 2 BHK 63.66499443 139
1 3 BHK 85.91880342 201
1 2 BHK 63.66499443 202
1 3 BHK 85.91044221 203
1 3 BHK 89.33017466 204
1 2 BHK 76.17985879 205
1 3 BHK 89.33017466 206
1 3 BHK 89.07004831 207
1 3 BHK 89.07004831 208
1 3 BHK 89.07004831 209
1 2 BHK 76.84968413 210
1 2 BHK 76.84968413 211
1 3 BHK 89.07004831 212
1 3 BHK 89.07004831 213
1 3 BHK 89.07004831 214
1 3 BHK 89.07004831 215
1 3 BHK 108.1103679 216
1 3 BHK 106.1603493 217
1 3 BHK 106.1603493 218
1 3 BHK 108.1103679 219
1 3 BHK 85.91044221 220
1 2 BHK 63.66499443 221
1 2 BHK 63.66499443 222
1 2 BHK 63.66499443 223
1 2 BHK 76.17985879 224
1 3 BHK 89.33017466 225
1 3 BHK 89.33017466 226
1 3 BHK 106.1603493 227
1 2 BHK 63.66499443 228
1 2 BHK 63.66499443 229
1 2 BHK 63.66499443 230
1 2 BHK 63.66499443 231
1 2 BHK 76.17985879 232
1 3 BHK 89.33017466 233
1 3 BHK 89.33017466 234
1 3 BHK 106.1603493 235
1 3 BHK 106.1603493 236
1 3 BHK 85.91044221 237
1 3 BHK 85.91044221 238
1 2 BHK 63.66499443 239
1 2 BHK 76.17985879 240
1 3 BHK 106.1603493 241
2 3 BHK 85.91880342 301
2 2 BHK 63.66499443 302
2 3 BHK 85.91044221 303
2 3 BHK 89.33017466 304
2 2 BHK 76.17985879 305
2 3 BHK 89.33017466 306
2 3 BHK 89.07004831 307
2 3 BHK 89.07004831 308
2 3 BHK 89.07004831 309
2 2 BHK 76.84968413 310
2 2 BHK 76.84968413 311
2 3 BHK 89.07004831 312
2 3 BHK 89.07004831 313
2 3 BHK 89.07004831 314
2 3 BHK 89.07004831 315
2 3 BHK 108.1103679 316
2 3 BHK 106.1603493 317
2 3 BHK 106.1603493 318
2 3 BHK 108.1103679 319
2 3 BHK 85.91044221 320
2 2 BHK 63.66499443 321
2 2 BHK 63.66499443 322
2 2 BHK 63.66499443 323
2 2 BHK 76.17985879 324
2 3 BHK 89.33017466 325
2 3 BHK 89.33017466 326
2 3 BHK 106.1603493 327
2 2 BHK 63.66499443 328
2 2 BHK 63.66499443 329
2 2 BHK 63.66499443 330
2 2 BHK 63.66499443 331
2 2 BHK 76.17985879 332
2 3 BHK 89.33017466 333
2 3 BHK 89.33017466 334
2 3 BHK 106.1603493 335
2 3 BHK 106.1603493 336
2 3 BHK 85.91044221 337
2 3 BHK 85.91044221 338
2 2 BHK 63.66499443 339
2 2 BHK 76.17985879 340
2 3 BHK 106.1603493 341
3 3 BHK 85.91880342 401
3 2 BHK 63.66499443 402
3 3 BHK 85.91044221 403
3 3 BHK 89.33017466 404
3 2 BHK 76.17985879 405
3 3 BHK 89.33017466 406
3 3 BHK 89.07004831 407
3 3 BHK 89.07004831 408
3 3 BHK 89.07004831 409
3 2 BHK 76.84968413 410
3 2 BHK 76.84968413 411
3 3 BHK 89.07004831 412
3 3 BHK 89.07004831 413
3 3 BHK 89.07004831 414
3 3 BHK 89.07004831 415
3 3 BHK 108.1103679 416
3 3 BHK 106.1603493 417
3 3 BHK 106.1603493 418
3 3 BHK 108.1103679 419
3 3 BHK 85.91044221 420
3 2 BHK 63.66499443 421
3 2 BHK 63.66499443 422
3 2 BHK 63.66499443 423
3 2 BHK 76.17985879 424
3 3 BHK 89.33017466 425
3 3 BHK 89.33017466 426
3 3 BHK 106.1603493 427
3 2 BHK 63.66499443 428
3 2 BHK 63.66499443 429
3 2 BHK 63.66499443 430
3 2 BHK 63.66499443 431
3 2 BHK 76.17985879 432
3 3 BHK 89.33017466 433
3 3 BHK 89.33017466 434
3 3 BHK 106.1603493 435
3 3 BHK 106.1603493 436
3 3 BHK 85.91044221 437
3 3 BHK 85.91044221 438
3 2 BHK 63.66499443 439
3 2 BHK 76.17985879 440
3 3 BHK 106.1603493 441
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage - - -
Covered Parking - - -
Open Parking - - -
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Amenities Gym % not reported Amenities Swimming Pool % not reported Sub Structure Earth Work And Other Leveling Preparation Work % not reported
Sub Structure Foundation Footing Work % not reported Sub Structure Upto Plinth Level % not reported Sub Structure Sub-structure Flooring (Parking Floor, More Than One Floor Below General Ground Level) % not reported
Sub Structure Retaining Wall (All Types) % not reported Sup Structure Rcc Or Ms Framed Structure % not reported Sup Structure Masonry Construction % not reported
Sup Structure Plastering Inside , Outside & Ceiling % not reported Sup Structure Joinery: Doors, Windows, Ventilators Etc % not reported Sup Structure Basic Work Of Water Supply, Sanitary And Electrification % not reported
Sup Structure Dadoing, Skirting, Flooring, Tiles Work (All Types) % not reported Sup Structure Railing And Grill Fixing % not reported Finishing Works Electrification, Water Supply And Sanitary Finishing % not reported
Finishing Works Painting % not reported Finishing Works Fire Prevention And Fire Fighting Fitting And Fixture With Network % not reported Finishing Works Weather Proof Work(tile,concrete) % not reported
Finishing Works Wardrobe, Showcase, Kitchen Cabinet, Puja Work % not reported Finishing Works Elevation Work % not reported Finishing Works Internal And External Work Including Landscapes As Per Sanctioned Drawings % not reported
Internal Infrastructure Water Supply % not reported Internal Infrastructure Sewage And Drainage System % not reported Internal Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported
Internal Infrastructure Energy Management % not reported Internal Infrastructure Fire Protection And Fire Safety Requirements % not reported Internal Infrastructure Solid Waste Management And Disposal % not reported
Internal Infrastructure Emergency Evacuation Services % not reported External Infrastructure Water Supply % not reported External Infrastructure Internal Roads & Footpaths % not reported
External Infrastructure Sewage And Drainage System % not reported External Infrastructure Electricity Supply Transformer And Substation % not reported External Infrastructure Solid Waste Management And Disposal % not reported
External Infrastructure Emergency Evacuation Services % not reported External Infrastructure Storm Water Drains % not reported External Infrastructure Use Of Renewable Energy % not reported
External Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported External Infrastructure Fire Protection And Fire Safety Requirements % not reported External Infrastructure Sewage Treatment Plant (Stp) % not reported
External Infrastructure Parks & Tree Planting % not reported External Infrastructure Street Lighting % not reported Amenities Electricity % not reported
Amenities Smart Home Automation % not reported Amenities Cctv Surveillance % not reported Amenities Club House % not reported
Amenities Community Hall % not reported Amenities Outdoor Sports Facility % not reported Amenities Indoor Sports Facility % not reported
Amenities Parks % not reported Amenities Power Backup % not reported Amenities Piped Gas % not reported
Amenities Water And Sanitation % not reported Amenities Air Conditioning % not reported Common Areas Staircases % not reported
Common Areas Lifts % not reported Common Areas Corridor/lobbies % not reported Common Areas Fire Escapes % not reported
Common Areas Common Entrance And Exit For The Building/common Portico/foyer/verandah % not reported Common Areas Basement % not reported Common Areas Terrace % not reported
Common Areas Outer Wall % not reported Common Areas Open Parking Areas % not reported Common Areas Provision For Lodging Of Management Staff And Security Staff % not reported
Common Areas Water Conservation And Renewable Energy % not reported Common Areas Common Storage Spaces % not reported
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Promoter Registration Certificate
Promoter Pan Card
Promoter Address Proof
Affidavit
Fd 1 NA.Pdf
Fd 2 NA.Pdf
Fd 3 NA.Pdf
Fd 4 NA.Pdf
Fd 5 NA.Pdf
Fd 6 NA.Pdf
Fd 7 NA.Pdf
Fd 8 NA.Pdf
Fd 9 NA.Pdf
Fd 10 NA.Pdf
Fd 11 NA.Pdf
Fd 12 NA.Pdf
Fd 13 NA.Pdf
Fd 14 NA.Pdf
Fd 15 NA.Pdf
Fd 16 NA.Pdf
Fd 17 NA.Pdf
Fd 18 NA.Pdf
Pd 1 Self Attested PAN Card*( Annexure - 66 )
Pd 2 Commencement Certificate*( Annexure - 67 )
Pd 3 Electricity Permission Letter*( Annexure - 68 )
Pd 4 Water Permission Letter*( Annexure - 69 )
Pd 5 Approved Layout Plan*( Annexure - 70 )
Pd 6 Approved Building Plotting Plan*( Annexure - 71 )
Pd 7 Existing Layout Plan( Annexure - 72 )
Pd 8 Existing Section Plan And Specification( Annexure - 73 )
Pd 9 Sectional Drawing Of The Apartments*( Annexure - 74 )
Pd 10 Project Specifications*( Annexure - 75 )
Pd 11 Approved Section Of Building Infrastructure Plan Of Plotting*( Annexure - 76 )
Pd 12 Area Development Plan Of Project Area*( Annexure - 77 )
Pd 13 Certificate From Registered Engineer Indicating The Structural Safety Of The Building*( Annexure - 78 )
Pd 14 Advocate Search Report*( Annexure - 79 )
Pd 15 Urban Land Ceiling*( Annexure - 80 )
Pd 16 Collaboration Agreement Development Agreement Joint Development Agreement Other Agreement*( Annexure - 81 )
Pd 17 Change Of Land Use*( Annexure - 82 )
Pd 18 District Magistrate*( Annexure - 83 )
Pd 19 Conversion Certificate Under Section 95 Of The KLR Act 1964*( Annexure - 84 )
Pd 20 Any Other Document (Rights Title Interest Name)*( Annexure - 85 )
Pd 21 Proforma Of Agreement For Sale*( Annexure - 86 )
Pd 22 Proforma Of Allotment Letter*( Annexure - 87 )
Pd 24 Brochure*( Annexure - 89 )
Dc 1 Declaration (Form B)*( Annexure - 90 )
Dc 2 Section 3(1) Notarized Affidavit*( Annexure - 91 )
Dc 3 JD AFFIDAVIT CUM DECLARATION*( Annexure - 92 )
Noc 1 ESCOM Electricity*( Annexure - 93 )
Noc 2 KWSSB Water*( Annexure - 94 )
Noc 3 Approval NOC Under Section 109 Of KLR Act 1961( Annexure - 95 )
Noc 4 Approval NOC Under Section 14 Of The KTCP Act( Annexure - 96 )
Noc 5 Fire Force Department( Annexure - 97 )
Noc 6 Airport Authority Of India( Annexure - 98 )
Noc 7 KSPCB( Annexure - 99 )
Noc 8 SEIAA( Annexure - 100 )
Noc 9 BSNL( Annexure - 101 )
Noc 10 Lift Authorities( Annexure - 102 )
Noc 11 BMRCL( Annexure - 103 )
Noc 12 NOC In Case Of Building Proposals Abutting To Neighbouring Properties( Annexure - 104 )
Noc 13 Bangalore Urban Arts Commission( Annexure - 105 )
Noc 14 Inspector Of Factories Controller Of Explosives Railways( Annexure - 106 )
Noc 15 Coastal Regulation Zone Authority( Annexure - 107 )
Dr 1 Utilisation Certificate( Annexure - 108 )
Dr 2 Transfer Of Development Rights Certificate( Annexure - 109 )
Dr 3 Relinquishment Deed( Annexure - 110 )
Photo 1 Project Photo
Ed 1 21-08-2024
Ed 2 21-08-2024
Ed 3 21-08-2024
Ed 4 21-08-2024
Ed 5 21-08-2024
Ed 6 21-08-2024
Ed 7 21-08-2024
Ed 8 21-08-2024
Ed 9 21-08-2024
Ed 10 21-08-2024
Ed 11 21-08-2024
Ed 12 21-08-2024
Ed 13 21-08-2024
Ed 14 21-08-2024
Ed 15 21-08-2024
Ed 16 21-08-2024
Ed 17 04-09-2024
Ed 18 04-09-2024
Ed 19 04-09-2024
Ed 20 04-09-2024
Ed 21 04-09-2024
Ed 22 12-09-2024
Ld Rtc
Ld Mutation
Ld Encumbrance Certificate
Ld Conversion Order
Ld Khatha
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC
Account Number (RERA) 50200085510990
IFSC HDFC0002377
Branch Address Whitefield
Country/City