- RERA Number P51800005475
- Project Name A and O EMINENTE
- Project Type Others
- Project Status Under Construction
- State MAHARASHTRA
- District Mumbai Suburban
- Taluka Borivali
- Village Borivali
- Original Completion 31 December 2021
- Revised Completion 30 June 2021
- Project Area (in Sq.mt.) 3,554.26
- Total Buildings/Towers 1
- Documents 60 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role |
|---|---|
| PRAVIN GIRISH CHAMARIA | Authorized Signatory |
| CHETAN SUNDARJI BHANUSHALI | Authorized Signatory |
| MEENA CHETAN BHANUSHALI | Authorized Signatory |
| MAYA HIKMAT UDHAN | Authorized Signatory |
| DHANJI GANESHA PATEL | Authorized Signatory |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Basements | No. of Plinth | No. of Podium | No. of Slab | No. of Slits | No. of Open Parking | No. of Closed Parking |
|---|---|---|---|---|---|---|---|---|---|
| A and O EMINENTE | A and O EMINENTE- WING A TO E | 2021-06-30 | 1 | 1 | 0 | 24 | 1 | 0 | 119 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- A and O EMINENTE- WING A TO E
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 2BHK WING D | 59.99 | 1 | 0 |
| 1BHK Wing A | 34.91 | 40 | 40 |
| 1BHK WING A | 36.50 | 22 | 22 |
| 1BHK WING A | 35.5 | 22 | 22 |
| 1BHK WING A | 35.25 | 21 | 21 |
| 2BHK Wing A | 57.39 | 2 | 2 |
| 2BHK WING A | 55.43 | 1 | 1 |
| 1BHK WING B | 35.46 | 23 | 23 |
| 1BHK WING B | 34.75 | 23 | 23 |
| 1BHK WING B | 35.48 | 22 | 22 |
| 1BHK WING B | 36.15 | 23 | 23 |
| 1BHK WING B | 36.01 | 23 | 23 |
| 1BHK Wing B | 36.13 | 23 | 23 |
| 1BHK WING C | 36.18 | 10 | 10 |
| 1BHK WING C | 37.32 | 1 | 1 |
| 1BHK WING C | 35.46 | 23 | 23 |
| 1BHK WING C | 34.73 | 23 | 23 |
| 1BHK WING C | 36.15 | 23 | 23 |
| 1BHK WING C | 35.93 | 23 | 23 |
| 1BHK WING C | 36.09 | 23 | 23 |
| 1BHK WING C | 42.34 | 12 | 12 |
| 1BHK WING D | 42.34 | 23 | 14 |
| 1BHK WING D | 34.65 | 14 | 13 |
| 2BHK WING D | 62.19 | 1 | 1 |
| 1BHK WING D | 37.32 | 2 | 2 |
| 1BHK WING E | 36.13 | 15 | 6 |
| 1BHK WING E | 42.34 | 12 | 5 |
| 1BHK WING E | 34.73 | 17 | 14 |
| 1BHK WING E | 42.48 | 11 | 5 |
| 2BHK WING E | 63.47 | 1 | 1 |
| 1BHK WING E | 37.32 | 1 | 1 |
| 1BHK WING E | 36.14 | 14 | 10 |
| 1BHK WING D | 36.18 | 7 | 4 |
| 1BHK WING D | 34.73 | 17 | 15 |
| 1BHK WING E | 36.18 | 2 | 2 |
| 1BHK WING E | 36.23 | 5 | 2 |
| 1BHK WING E | 37.26 | 1 | 1 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 119 | 0 | 16 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 25% | Water Conservation Rainwater Harvesting 25% | Energy Management % not reported |
| Fire Protection And Fire Safety Requirements 25% | Electrical Meter Room Substation Receivingstation 25% | Aggregate Area Of Recreational Open Space 10% |
| Open Parking % not reported | Water Supply 25% | Sewerage % not reported |
| Storm Water Drains 25% | Landscaping Tree Planting % not reported | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water 25% | Solid Waste Management Disposal 25% |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- A and O EMINENTE- WING A TO E
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | STATE BANK OF INDIA |
|---|---|
| IFSC | SBIN0050458 |