Arkade Earth RERA Details - P51800022666, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Arkade Earth under registration P51800022666 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800022666
  • Project Name ARKADE EARTH - HAZEL
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Kurla
  • Village Kurla
  • Original Completion 30 December 2023
  • Revised Completion 30 December 2023
  • Project Area (in Sq.mt.) 227.4
  • Total Buildings/Towers 1
  • Documents 12 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 10 October 2019 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Arkade Developers Private Limited
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Arkade AdorniaJayprakash Nagar Road No. 2 Goregaon East Mumbai 400 063 2102.7CompletedResidential / Group Housing1822016-12-312017-05-17NoNA
Jeevan SaritaJeevan Sarita CHS Ltd Plot No 60 Tejpal Schem Vile Parle East Mumbai 4000571849.5CompletedResidential / Group Housing1632016-06-302016-06-30NoNA
MahantMahant CHS Ltd Plot No 59 CTS No 932 Mahant Road Vile Parle East Mumbai 400057772.6CompletedResidential / Group Housing1182012-12-312013-03-01NoNA
GangadharGangadhar Nagar CHS Ltd Sant Dyaneshwar Marg Shantivan Borivali East Mumbai 400 0662435.6CompletedIndustrial1902013-12-312013-09-21NoNA

Promoters, Co-promoters & Members

NameRoleAddress
Amit Mangilal JainManaging DirectorMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
ARKADE EARTH - HAZEL ARKADE EARTH - HAZEL 0 0 25 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 90
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 67 units · avg area 43.17 Sq.mt.
2 BHK 23 units · avg area 62.89 Sq.mt.
  • ARKADE EARTH - HAZEL
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 62.89 23 16
1BHK 43.2 21 13
1BHK 43.39 23 16
1BHK 42.92 23 16
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting 100.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 95.0% Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 90.0% Aggregate Area Of Recreational Open Space % not reported Open Parking 100.0%
Basement 100.0% Club House With Swimming Pool And Other Amenities 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • ARKADE EARTH - HAZEL
ARKADE EARTH - HAZEL · Overall Progress 91%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Layout Approval.Pdf.Pdf
2 1 IOD.Pdf.Pdf
3 2 IOD.Pdf.Pdf
4 3 IOD.Pdf.Pdf
5 PAN ADPL.Pdf.Pdf
6 Hazel OC.Pdf.Pdf
7 Title Report.Pdf.Pdf
8 Form B ADPL.Pdf.Pdf
9 Echjay 9th Sep.Pdf.Pdf
10 Hazel Draft Agreement.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank INDUSIND BANK
IFSC INDB0000006
Branch Address GROUND FLOOR, MAKER CHAMBER IV, NARIMAN POINT, 400 021
Country/City