Blue Star Crystal Apartment RERA Details - P51800049927, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Blue Star Crystal Apartment under registration P51800049927 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800049927
  • Project Name BLUE STAR CRYSTAL CHSL
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Borivali
  • Village Borivali
  • Original Completion 12 July 2027
  • Revised Completion 12 July 2027
  • Project Area (in Sq.mt.) 2,514.0
  • Total Buildings/Towers 1
  • Documents 24 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 06 March 2023 Expected commencement of civil works and foundation on site.
Original Completion 12 July 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 12 July 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name PARADIGM BLUE STAR LLP

Promoters, Co-promoters & Members

NameRoleAddress
DHRUVAL KIRIT MEHTAPartnerMumbai Suburban, MAHARASHTRA
TIMIR RAMESH MEHTAPartnerMumbai Suburban, MAHARASHTRA
ANUJ RAMESHCHANDRA MEHTAPartnerMumbai Suburban, MAHARASHTRA
RUPA KIRIT MEHTAPartnerMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
BLUE STAR CRYSTAL CHSL BLUE STAR CRYSTAL CHSL 0 68 19 FULL CC 19 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 47
Configurations 6
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 7 units · avg area 64.48 Sq.mt.
3 BHK 22 units · avg area 97.57 Sq.mt.
5 BHK 3 units · avg area 140.93 Sq.mt.
MP ROOM 2 units · avg area 5.81 Sq.mt.
Shop 10 units · avg area 30.73 Sq.mt.
Office space 3 units · avg area 112.75 Sq.mt.
  • BLUE STAR CRYSTAL CHSL
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
5BHK & more 174.19 1 1
MP ROOM 5.81 2 2
EXISTING MEMBER 3BHK 112.6 1 1
EXISTING MEMBER 2BHK 58.34 1 1
EXISTING MEMBER 2BHK 63.73 1 1
Shop 43.38 1 1
Office space 226.03 1 1
Shop 34.74 1 1
Office space 76.83 1 1
Shop 27.78 1 1
Shop 31.77 1 1
Shop 33.01 1 1
EXISTING MEMBER 3BHK 80.36 1 1
EXISTING MEMBER 2BHK 65.86 5 5
Shop 36.79 1 1
EXISTING MEMBER 3BHK 84.26 5 5
EXISTING MEMBER 3 BH 85.93 1 1
EXISTINGMEMBER3.5BHK 95.32 1 1
Shop 19.97 1 1
Shop 25.27 1 1
Shop 27.31 2 2
3BHK 107.02 6 6
Office space 35.4 1 1
EXISTING MEMBER 3BHK 107.58 2 2
Existing Member 3bhk 107.02 4 4
5BHK & more 153.29 1 1
EXISTING MEMBER 3BHK 80.45 2 2
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 65.0% Water Supply 75.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 80.0%
Storm Water Drains 80.0% Landscaping & Tree Planting 55.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 85.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 95.0%
Electrical Meter Room, Sub-station, Receiving Station 70.0% Aggregate Area Of Recreational Open Space 85.0% Open Parking 60.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BLUE STAR CRYSTAL CHSL
BLUE STAR CRYSTAL CHSL · Overall Progress 75%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
In Progress
% Work98%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work85%
Sanitary Fittings within the flats / premises
In Progress
% Work85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work85%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 PLAN.Pdf.Pdf
2 IOD Signed.Pdf.Pdf
3 Blue Star IOD PLAN 2 2.Pdf.Pdf
4 Blue Star IOD PLAN 3 3.Pdf.Pdf
5 Blue Star IOD PLAN 4 4.Pdf.Pdf
6 Blue Star IOD PLAN 5 5.Pdf.Pdf
7 Blue Star IOD PLAN 6 6.Pdf.Pdf
8 Blue Star IOD PLAN 7 End.Pdf.Pdf
9 RERA LAYOUT 1 1.Pdf.Pdf
10 RERA LAYOUT 2 2.Pdf.Pdf
11 RERA LAYOUT 3 3.Pdf.Pdf
12 RERA LAYOUT 4 4.Pdf.Pdf
13 RERA LAYOUT 5 5.Pdf.Pdf
14 RERA LAYOUT 6 End.Pdf.Pdf
15 Blue Star LLP Pan Card.Pdf.Pdf
16 Format A Legal Title Report.Pdf.Pdf
17 Title Certificate (Advocate Hirleker).Pdf.Pdf
18 Promoter Form B (1).Pdf.Pdf
19 Model Allotment Letter.Pdf.Pdf
20 ALLOTMENT LETTER.Pdf.Pdf
21 Proforma Of Agreement For Sale.Pdf.Pdf
22 DEV AFS.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0000145
Branch Address BORIVALI WEST
Country/City