residential Ready to Move Source: rera.mh

DJ Homes JB Amore RERA Details - P51800026915, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for DJ Homes JB Amore under registration P51800026915 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800026915
  • Project Name DJ AMORE
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Kurla
  • Village Kurla
  • Original Completion 05 October 2023
  • Revised Completion 05 October 2023
  • Project Area (in Sq.mt.) 429.2
  • Total Buildings/Towers 1
  • Documents 12 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 03 November 2020 Expected commencement of civil works and foundation on site.
Original Completion 05 October 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 05 October 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Individual
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
JB SHINEplot no 21a collector colony296CompletedResidential / Group Housing1152016-11-072019-11-01NoNA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
DJ AMORE DJ AMORE 0 0 9 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 22
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 14 units · avg area 39.23 Sq.mt.
2 BHK 7 units · avg area 62.03 Sq.mt.
3 BHK 1 unit · avg area 75.60 Sq.mt.
  • DJ AMORE
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 38.72 7 7
3BHK 75.6 1 0
2BHK 62.03 7 5
1BHK 39.75 7 6
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 50.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 50.0% Solid Waste Management And Disposal 50.0%
Water Conservation /Rain Water Harvesting 50.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 75.0%
Electrical Meter Room, Sub-station, Receiving Station 50.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • DJ AMORE
DJ AMORE · Overall Progress 80%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work90%
Sanitary Fittings within the flats / premises
In Progress
% Work80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work25%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 DRAWINGS DJ AMORE.Pdf.Pdf
2 Pan Card.Pdf.Pdf
3 Amendment Letter.Pdf.Pdf
4 Flat Details.Pdf.Pdf
5 RERA Carpet.Pdf.Pdf
6 DJ Amore Title ( Pardeep ).Pdf.Pdf
7 DJ Amore Title ( Pran ).Pdf.Pdf
8 FORM B CO PROMOTOR.Pdf.Pdf
9 FORM B FOR DEVELOPER.Pdf.Pdf
10 Sale Agreement DJ AMORE Updated.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank AU SMALL FINANCE BANK LIMITED
IFSC AUBL0002340
Branch Address ANDHERI KURLA ROAD MUMBAI
Country/City