RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P51800001462
- Project Name TRINITY CO OP HSG SOC LTD
- Project Type Others
- Project Status Ready to Move
- State Maharashtra
- District Mumbai Suburban
- Taluka Kurla
- Village Kurla
- Original Completion 30 December 2019
- Revised Completion 30 December 2019
- Project Area (in Sq.mt.) 4,769.8
- Total Buildings/Towers 4
- Documents 2 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role | Address |
|---|---|---|
| PRASHANT GOPAL SHARMA | Partner | Mumbai Suburban, MAHARASHTRA |
| DIKSHANT GOPAL SHARMA | Partner | Mumbai Suburban, MAHARASHTRA |
| HIMANSHU PRASHANT SHARMA | Partner | Mumbai Suburban, MAHARASHTRA |
| YUGANK DIKSHANT SHARMA | Partner | Mumbai Suburban, MAHARASHTRA |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | No. of Open Parking | No. of Closed Parking | No. of Floors | No. of Habitable Floor | No. of Sanctioned Apartment | Wing Name |
|---|---|---|---|---|---|---|---|
| TRINITY CO OP HSG SOC LTD | TRINITY A | 0 | 33 | 16 | 0 | 0 | NA |
| TRINITY CO OP HSG SOC LTD | TRINITY B | 0 | 47 | 16 | 0 | 0 | NA |
| TRINITY CO OP HSG SOC LTD | TRINITY C | 0 | 47 | 16 | 0 | 0 | NA |
| TRINITY CO OP HSG SOC LTD | TRINITY D | 0 | 123 | 16 | 0 | 0 | NA |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- TRINITY A
- TRINITY B
- TRINITY C
- TRINITY D
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 2 BHK | 56.41 | 9 | 9 |
| 2 BHK | 56.24 | 9 | 9 |
| 2 BHK | 69.81 | 2 | 2 |
| 2 BHK | 51.48 | 2 | 2 |
| 2 BHK | 51.57 | 2 | 2 |
| 2 BHK | 51.74 | 2 | 2 |
| 2 BHK | 56.13 | 7 | 7 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 2 BHK | 56.31 | 19 | 18 |
| 2 BHK | 51.76 | 1 | 1 |
| 2 BHK | 56.52 | 9 | 8 |
| 2 BHK | 56.28 | 10 | 9 |
| 2 BHK | 57.25 | 1 | 1 |
| 2 BHK | 55.84 | 1 | 1 |
| 1 BHK | 44.29 | 2 | 2 |
| 2 BHK | 56.2 | 1 | 1 |
| 2 BHK | 51.61 | 1 | 1 |
| 2BHK | 51.58 | 1 | 1 |
| 2 BHK | 51.57 | 1 | 1 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 2BHK | 51.34 | 1 | 1 |
| 2BHK | 51.37 | 1 | 1 |
| 2 BHK | 51.58 | 1 | 1 |
| 2 BHK | 55.67 | 1 | 1 |
| 2 BHK | 56.25 | 10 | 9 |
| 2 BHK | 51.44 | 1 | 1 |
| 2 BHK | 56.24 | 11 | 11 |
| 2 BHK | 55.92 | 11 | 11 |
| 2 BHK | 56.0 | 10 | 10 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| SHOP | 15.29 | 1 | 1 |
| SHOP | 16.17 | 1 | 1 |
| SHOP | 16.81 | 1 | 1 |
| SHOP | 20.25 | 1 | 1 |
| SHOP | 19.64 | 1 | 0 |
| 3BHK | 94.47 | 1 | 1 |
| SHOP | 27.44 | 1 | 1 |
| SHOP | 17.33 | 1 | 1 |
| 3 BHK | 94.6 | 12 | 6 |
| 2 BHK | 67.21 | 13 | 11 |
| 3 BHK | 92.38 | 12 | 6 |
| 3 BHK | 92.68 | 1 | 1 |
| 3 BHK | 94.3 | 1 | 1 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads & Footpaths % not reported | Water Supply 90.0% | Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0% |
| Storm Water Drains 100.0% | Landscaping & Tree Planting 100.0% | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage And Sullage Water % not reported | Solid Waste Management And Disposal % not reported |
| Water Conservation /Rain Water Harvesting 100.0% | Energy Managemcnt % not reported | Fire Protection And Fire Safety Requirements 100.0% |
| Electrical Meter Room, Sub-station, Receiving Station 100.0% | Aggregate Area Of Recreational Open Space 100.0% | Open Parking % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- TRINITY A
- TRINITY B
- TRINITY C
- TRINITY D
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | THE COSMOS CO OPERATIVE BANK LIMITED |
|---|---|
| IFSC | COSB0000919 |
| Branch Address | S M SHETTY SCHOOL POWAI MUMBAI |