Gurukrupa Marina Enclave RERA Details - P51800032311, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Gurukrupa Marina Enclave under registration P51800032311 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800032311
  • Project Name Marina Enclave Wings OP Phase III
  • Project Type Others
  • Project Status Ready to Move
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Borivali
  • Village Borivali
  • Original Completion 30 June 2023
  • Revised Completion 30 June 2023
  • Project Area (in Sq.mt.) 4,445.0
  • Total Buildings/Towers 2
  • Documents 93 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 29 December 2021 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Gurukrupa Developers D.N.Nagar Project
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Marina Enclave Wings A to I CTS No 507 Survey No. 44 1 Village Malvani Malad W Mumbai 400 05.17219.24CompletedResidential / Group Housing97082016-12-302016-12-28NoNA
Marina Enclave Wings JKL Phase- ICTS 507 Survey No 44 1 Village Malvani Malad West Mumbai 400 095.7928.92CompletedResidential / Group Housing32582019-12-312019-06-04NoNA
Marina Enclave Wings MN Phase- IICTS No. 507 Survey Nol. 44 1 Village Malvani Malad West Mumbai 400 0955431.21CompletedResidential / Group Housing21722020-12-312020-03-23NoNA

Promoters, Co-promoters & Members

NameRoleAddress
Chetan Navinchandra PatelPartnerMumbai Suburban, MAHARASHTRA
Chetan Mansukhlal KothariPartnerMumbai Suburban, MAHARASHTRA
Hitesh Hansraj PatelPartnerMumbai Suburban, MAHARASHTRA
Guruashish Buildcon LLP Director MansukhA SurejaPartnerMumbai Suburban, MAHARASHTRA
SKC Trading Pvt Ltd Director Samir M SurejaPartnerMumbai Suburban, MAHARASHTRA
Mansukh Arjanbhai SurejaPartnerMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Marina Enclave Wings OP Phase III O Wing 0 113 25 0 0 NA
Marina Enclave Wings OP Phase III P Wing 0 114 25 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 175
Configurations 5
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 128 units · avg area 59.14 Sq.mt.
3 BHK 44 units · avg area 77.95 Sq.mt.
Unit ldg unldg room 1 unit · avg area 36.35 Sq.mt.
unit Dr cnsltg room 1 unit · avg area 20.25 Sq.mt.
Unit Super market 1 unit · avg area 301.43 Sq.mt.
  • O Wing
  • P Wing
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 59.22 44 0
2BHK 59.02 20 0
3BHK 77.9 22 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains % not reported Landscaping & Tree Planting 50.0% Street Lighting % not reported
Community Buildings 100.0% Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • O Wing
  • P Wing
O Wing · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 31032021Marina Enclave 1.Pdf.Pdf
2 31032021Marina Enclave 2.Pdf.Pdf
3 31032021Marina Enclave 3.Pdf.Pdf
4 31032021Marina Enclave 4.Pdf.Pdf
5 31032021Marina Enclave 5.Pdf.Pdf
6 31032021Marina Enclave 6.Pdf.Pdf
7 31032021Marina Enclave 7.Pdf.Pdf
8 31032021Marina Enclave 8.Pdf.Pdf
9 31032021Marina Enclave 9.Pdf.Pdf
10 31032021Marina Enclave 10.Pdf.Pdf
11 31032021Marina Enclave 11.Pdf.Pdf
12 31032021Marina Enclave 12.Pdf.Pdf
13 31032021Marina Enclave 13.Pdf.Pdf
14 31032021Marina Enclave 14.Pdf.Pdf
15 31032021Marina Enclave 15.Pdf.Pdf
16 31032021Marina Enclave 16.Pdf.Pdf
17 With Signature PHASE PLAN PDF.Pdf.Pdf
18 31032021Marina Enclave 17.Pdf.Pdf
19 31032021Marina Enclave 18.Pdf.Pdf
20 31032021Marina Enclave 19.Pdf.Pdf
21 31032021Marina Enclave 20.Pdf.Pdf
22 31032021Marina Enclave 21.Pdf.Pdf
23 31032021Marina Enclave 22.Pdf.Pdf
24 31032021Marina Enclave 23.Pdf.Pdf
25 31032021Marina Enclave 24.Pdf.Pdf
26 31032021Marina Enclave 25.Pdf.Pdf
27 31032021Marina Enclave 26.Pdf.Pdf
28 31032021Marina Enclave 27.Pdf.Pdf
29 31032021Marina Enclave 28.Pdf.Pdf
30 31032021Marina Enclave 29.Pdf.Pdf
31 31032021Marina Enclave 30.Pdf.Pdf
32 31032021Marina Enclave 31.Pdf.Pdf
33 31032021Marina Enclave 32.Pdf.Pdf
34 31032021Marina Enclave 33.Pdf.Pdf
35 31032021Marina Enclave 34.Pdf.Pdf
36 27072018 Marina Plan 1.Pdf.Pdf
37 27072018 Marina Plan 2.Pdf.Pdf
38 27072018 Marina Plan 3.Pdf.Pdf
39 27072018 Marina Plan 4.Pdf.Pdf
40 27072018 Marina Plan 5.Pdf.Pdf
41 27072018 Marina Plan 6.Pdf.Pdf
42 27072018 Marina Plan 7.Pdf.Pdf
43 27072018 Marina Plan 8.Pdf.Pdf
44 27072018 Marina Plan 9.Pdf.Pdf
45 27072018 Marina Plan 10.Pdf.Pdf
46 27072018 Marina Plan 11.Pdf.Pdf
47 27072018 Marina Plan 12.Pdf.Pdf
48 27072018 Marina Plan 13.Pdf.Pdf
49 27072018 Marina Plan 14.Pdf.Pdf
50 27072018 Marina Plan 15.Pdf.Pdf
51 27072018 Marina Plan 16.Pdf.Pdf
52 27072018 Marina Plan 17.Pdf.Pdf
53 27072018 Marina Plan 18.Pdf.Pdf
54 27072018 Marina Plan 19.Pdf.Pdf
55 27072018 Marina Plan 20.Pdf.Pdf
56 27072018 Marina Plan 21.Pdf.Pdf
57 27072018 Marina Plan 22.Pdf.Pdf
58 27072018 Marina Plan 23.Pdf.Pdf
59 27072018 Marina Plan 24.Pdf.Pdf
60 27072018 Marina Plan 25.Pdf.Pdf
61 27072018 Marina Plan 26.Pdf.Pdf
62 27072018 Marina Plan 27.Pdf.Pdf
63 Architect Total Layout Certificate.Pdf.Pdf
64 PHASE PLAN.Pdf.Pdf
65 Total Layout Certificate By Firm.Pdf.Pdf
66 27072018 Marina Plan No 1 To 6.Pdf.Pdf
67 27072018Marina Plan No 7 To 12.Pdf.Pdf
68 27072018Marina Plan No13 To 18.Pdf.Pdf
69 27072018Marina Plan No19 To 23.Pdf.Pdf
70 270720182018Marina Plan No24 To 27.Pdf.Pdf
71 31032021Marina Enclave Plan 1 To 3.Pdf.Pdf
72 31032021Marina Enclave Plan 4 To 7.Pdf.Pdf
73 31032021Marina Enclave Plan 8 To 10.Pdf.Pdf
74 31032021Marina Enclave Plan 11 To 13.Pdf.Pdf
75 31032021Marina Enclave Plan 14 To 17.Pdf.Pdf
76 31032021Marina Enclave Plan 18 To 20.Pdf.Pdf
77 31032021Marina Enclave Plan 21 To 23.Pdf.Pdf
78 31032021Marina Enclave Plan 24 To 27.Pdf.Pdf
79 31032021Marina Enclave Plan 28 To 30.Pdf.Pdf
80 31032021Marina Enclave Plan 31 To 34.Pdf.Pdf
81 PAN Of GDDN.Pdf.Pdf
82 CFO Letter150917.PDF.Pdf
83 CFO NOC Letter17102019.Pdf.Pdf
84 Self Certificates For Non Encumbrance.Pdf.Pdf
85 Self Declaration For No Litigation.Pdf.Pdf
86 IOD.Pdf.Pdf
87 Tiitle Certificate Format A As Per Order 28with Annexure.PDF.Pdf
88 Notarised Form B Scan.Pdf.Pdf
89 Title Certificate.PDF.Pdf
90 Authorisation Letter Of Partners.Pdf.Pdf
91 ProformaAllotment Final.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0000182
Branch Address Building no 3 wing G Thankur Enclave Sankul Thakur Complex Kandivali East mumbai 400101