- RERA Number P51800017171
- Project Name AURIS GALLERIA
- Project Type Commercial
- Project Status Ready to Move
- State Maharashtra
- District Mumbai Suburban
- Taluka Andheri
- Village Andheri
- Original Completion 30 December 2023
- Revised Completion 30 December 2023
- Project Area (in Sq.mt.) 1,976.79
- Total Buildings/Towers 1
- Documents 14 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role | Address | |
|---|---|---|---|
| Jitendra Natwarlal Sheth | Director | GsYpUrZ/wwqd99TU7XExcLjePMgcONdI3lWoswxaorsm5/GgZN21JeE2GkLG1iDv, Mumbai Suburban, MAHARASHTRA | a8x4405/C0IIHnqwpfDQsjJ4j7FOxKiozTIwpMk9swcf1hJuwUINuKzHX1M7k6aN |
| Kirti Kediya | Director | Mumbai Suburban, MAHARASHTRA | - |
Land, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
| Address DT64oWxLVIgFsko8fXmHt5dJBPWW6RSIBg7cEY0Z7V1reluUkWHhDCX/VnDFQSwt |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | No. of Open Parking | No. of Closed Parking | No. of Floors | No. of Habitable Floor | No. of Sanctioned Apartment | Wing Name |
|---|---|---|---|---|---|---|---|
| AURIS GALLERIA | AURIS GALLERIA | 0 | 252 | 7 | 0 | 0 | NA |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- AURIS GALLERIA
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| SHOP | 85.4 | 1 | 1 |
| SHOP | 83.8 | 1 | 1 |
| SHOP | 83.95 | 1 | 1 |
| SHOP | 83.9 | 5 | 5 |
| SHOP | 109.35 | 1 | 0 |
| SHOP | 71.8 | 1 | 0 |
| SHOP | 108.65 | 1 | 0 |
| SHOP | 96.25 | 1 | 1 |
| SHOP | 57.05 | 3 | 3 |
| SHOP | 92.75 | 1 | 1 |
| SHOP | 75.3 | 3 | 1 |
| SHOP | 94.05 | 1 | 1 |
| SHOP | 80.0 | 1 | 1 |
| SHOP | 94.6 | 1 | 1 |
| SHOP | 95.85 | 1 | 1 |
| SHOP | 48.85 | 6 | 6 |
| SHOP | 92.15 | 1 | 1 |
| SHOP | 77.7 | 1 | 1 |
| SHOP | 46.3 | 3 | 3 |
| SHOP | 109.65 | 3 | 3 |
| SHOP | 41.9 | 21 | 21 |
| SHOP | 47.85 | 3 | 3 |
| SHOP | 95.6 | 1 | 1 |
| SHOP | 46.95 | 3 | 3 |
| SHOP | 45.35 | 3 | 3 |
| SHOP | 44.45 | 3 | 3 |
| SHOP | 83.85 | 1 | 1 |
| SHOP | 118.75 | 1 | 1 |
| SHOP | 43.55 | 3 | 3 |
| SHOP | 60.45 | 3 | 3 |
| SHOP | 87.2 | 1 | 1 |
| SHOP | 34.85 | 1 | 1 |
| SHOP | 97.4 | 1 | 1 |
| SHOP | 46.0 | 3 | 3 |
| SHOP | 42.55 | 3 | 3 |
| SHOP | 41.95 | 3 | 3 |
| SHOP | 52.3 | 3 | 3 |
| SHOP | 115.05 | 1 | 1 |
| SHOP | 97.9 | 1 | 1 |
| SHOP | 44.75 | 3 | 3 |
| SHOP | 89.05 | 1 | 1 |
| SHOP | 90.9 | 1 | 1 |
| SHOP | 105.0 | 3 | 3 |
| SHOP | 92.0 | 1 | 0 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads & Footpaths % not reported | Water Supply 40.0% | Sewerage (Chamber, Lines, Septic Tank , Stp) 90.0% |
| Storm Water Drains 80.0% | Landscaping & Tree Planting 45.0% | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage And Sullage Water 50.0% | Solid Waste Management And Disposal 20.0% |
| Water Conservation /Rain Water Harvesting 45.0% | Energy Managemcnt 15.0% | Fire Protection And Fire Safety Requirements 90.0% |
| Electrical Meter Room, Sub-station, Receiving Station 60.0% | Aggregate Area Of Recreational Open Space 15.0% | Open Parking % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- AURIS GALLERIA
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | STATE BANK OF INDIA |
|---|---|
| IFSC | SBIN0004791 |
| Branch Address | 2nd Floor The Arcade World Trade Center Cuffe Parade Mumbai 400005 |