residential Under Construction Source: rera.mh

Neelkanth Complex Panvel RERA Details - P52000077406, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Neelkanth Complex Panvel under registration P52000077406 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52000077406
  • Project Name Neelkanth Complex
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Raigarh
  • Taluka Panvel
  • Village Panvel
  • Original Completion 31 December 2027
  • Revised Completion 31 December 2027
  • Project Area (in Sq.mt.) 2,097.0
  • Total Buildings/Towers 1
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 13 August 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Neelkanth Mahadev Developers

Promoters, Co-promoters & Members

NameRoleAddress
Abdul Gani Abdul Rehman DadanPartnerThane, MAHARASHTRA
Ratanlal Tararam ChoudharyPartnerRaigarh, MAHARASHTRA
Arvind Bhanji RavriyaPartnerRaigarh, MAHARASHTRA
Riya Narayan RavriyaPartnerRaigarh, MAHARASHTRA
Kailash Gokar KarotraPartnerThane, MAHARASHTRA
Raghu Ambavi PatelPartnerRaigarh, MAHARASHTRA
Kaluram Pukharamji ChoudharyPartnerRaigarh, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Neelkanth Complex Neelkanth Complex 3 1 8 6 6 100 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Neelkanth Complex
Neelkanth Complex · Overall Progress 15%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
In Progress
% Work70%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
61 Form 2A (FY 2025 2026).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank FEDERAL BANK
IFSC FDRL0001750
Branch Address SHOP NOS.4, 5 & 6, GROUND FLOOR, ANANT PLOT NO.31, SECTOR 4, NAVI MUMBAI
Country/City