Paradise Sai World Icon RERA Details - P52000023156, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Paradise Sai World Icon under registration P52000023156 in Navi Mumbai, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52000023156
  • Project Name SAI ICON
  • Project Type Residential
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Raigarh
  • Taluka Panvel
  • Village Owe
  • Original Completion 30 December 2024
  • Project Area (in Sq.mt.) 3,042.47
  • Total Buildings/Towers 1
  • Documents 52 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 04 December 2019 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2024 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Paradise Infra-con Pvt Ltd
Website www.paradisegroup.co.in
Experience Details
Project NameAddressLand AreaType of ProjectBuild Plot CountApartment countProject End Date
SAI MOKSHSECTOR 15 KHARGHAR NAVI MUMBAI2410.68Residential1732015-06-19
SAI GANGASECTOR 5 ULWE1949Residential1622017-01-11
SAI FORTUNESECTOR 8 ULWE2349Residential1992016-11-21
SAI SAHILSECTOR 5 ULWE NAVI MUMBAI1449Residential1502017-04-28
SAI HARMONYSECTOR 21 ULWE2650Residential11152016-07-15
SAI SAPPHIRESECTOR 20 ULWE NAVI MUMBAI4000Residential11622015-07-02
SAI SPRINGSECTOR 35G KHARGHAR NAVI MUMBAI5000Residential11482016-07-21
SAI MIRACLESECTOR 35E4900Residential11102016-07-22
SAI CRYSTALSECTOR 35D KHARGHAR NAVI MUMBAI6049Residential11662016-09-30
SAI WONDERSECTOR 35F KHARGHAR NAVI MUMBAI2200Residential1952017-05-09
SAI SOLITAIRESECTOR 35H KHARGHAR NAVI MUMBAI3400Residential1832017-06-21
Other Description NA

Promoters, Co-promoters & Members

NameRole
Madhu Bhagwandas BathijaChairperson
Manish Madhu BathijaManaging Director
Amit Madhu BathijaDirector
Umesh Kumar Bhagwatprasad UpadhyayAuthorized Signatory

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
SAI ICON SAI ICON 2024-12-28 0 1 1 14 1 0 60

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 120
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 52 units · avg area 36.77 Sq.mt.
2 BHK 52 units · avg area 48.64 Sq.mt.
Office space 8 units · avg area 19.00 Sq.mt.
Shop 8 units · avg area 24.50 Sq.mt.
  • SAI ICON
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 36.77 52 23
2BHK 48.64 52 23
Office space 19 8 2
Shop 24.5 8 4
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 60 52 100
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Conservation Rainwater Harvesting 100% Energy Management 50%
Fire Protection And Fire Safety Requirements 40% Electrical Meter Room Substation Receivingstation 30% Aggregate Area Of Recreational Open Space 100%
Open Parking % not reported Water Supply 25% Sewerage 50%
Storm Water Drains 65% Landscaping Tree Planting 25% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SAI ICON
SAI ICON · Overall Progress 90%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
In Progress
% Work90%
X number of Podiums
In Progress
% Work90%
Stilt Floor
In Progress
% Work90%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work70%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work92%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work80%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
1 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval / NA Order For Plotted Development
2 Building Plan Approval / NA Order For Plotted Development
3 Building Plan Approval / NA Order For Plotted Development
4 Building Plan Approval / NA Order For Plotted Development
5 Building Plan Approval / NA Order For Plotted Development
6 Building Plan Approval / NA Order For Plotted Development
7 Building Plan Approval / NA Order For Plotted Development
8 Building Plan Approval / NA Order For Plotted Development
9 Building Plan Approval / NA Order For Plotted Development
1 Commencement Certificates / NA Order For Plotted Development
2 Commencement Certificates / NA Order For Plotted Development
1 Declaration About Commencement Certificate
1 Declaration In FORM B
2 Declaration In FORM B
3 Declaration In FORM B
1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
1 Engineer’S Certificate On Cost Incurred On Project (Form 2)
2 Engineer’S Certificate On Cost Incurred On Project (Form 2)
3 Engineer’S Certificate On Cost Incurred On Project (Form 2)
4 Engineer’S Certificate On Cost Incurred On Project (Form 2)
5 Engineer’S Certificate On Cost Incurred On Project (Form 2)
6 Engineer’S Certificate On Cost Incurred On Project (Form 2)
7 Engineer’S Certificate On Cost Incurred On Project (Form 2)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2023-24)
1 Disclosure Of Sold/ Booked Inventory
2 Disclosure Of Sold/ Booked Inventory
1 CERSAI Details
2 CERSAI Details
1 Disclosure Of Interest In Other Real Estate Organizations
2 Disclosure Of Interest In Other Real Estate Organizations
3 Disclosure Of Interest In Other Real Estate Organizations
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020-21)
2 Annual Audit Report Of Statutory CA (Form 5) (FY 2020-21)
3 Annual Audit Report Of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023-24)
1 Proforma Of Allotment Letter
2 Proforma Of Allotment Letter
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank Indian Overseas Bank
IFSC IOBA0001425
Country/City