Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Under Construction Source: rera.mh

TPV The Elements RERA Details - P51700079613, Navi Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for TPV The Elements under registration P51700079613 in Navi Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700079613
  • Project Name The Elements
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Navi Mumbai (M Corp.)
  • Original Completion 31 December 2031
  • Revised Completion 31 December 2031
  • Project Area (in Sq.mt.) 13,512.6
  • Total Buildings/Towers 6
  • Documents 50 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 17 March 2025 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2031 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2031 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name TPV Ventures LLP

Promoters, Co-promoters & Members

NameRoleAddress
Ganesh Valji VaidPartnerThane, MAHARASHTRA
Mahadev Pragji GothiPartnerThane, MAHARASHTRA
Everest Nisarg Greenland Developers Private LimitedPartnerThane, MAHARASHTRA
Murji Bhanji GamiPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
The Elements Wing A 105 173 51 46 40 82 NA
The Elements Wing B 117 185 51 46 46 176 NA
The Elements Wing C 117 185 51 46 46 94 NA
The Elements Wing D 117 185 51 46 46 94 NA
The Elements Wing E 105 174 51 46 46 84 NA
The Elements Commercial 108 57 6 6 6 51 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 581
Configurations 5
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 36 units · avg area 49.85 Sq.mt.
2 BHK 207 units · avg area 69.59 Sq.mt.
3 BHK 246 units · avg area 117.82 Sq.mt.
4 BHK 41 units · avg area 150.44 Sq.mt.
Shop 51 units · avg area 56.70 Sq.mt.
  • Wing A
  • Wing B
  • Wing C
  • Wing D
  • Wing E
  • Commercial
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
4BHK 150.44 41 0
2BHK 75.05 41 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Wing A
  • Wing B
  • Wing C
  • Wing D
  • Wing E
  • Commercial
Wing A · Overall Progress 9%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Proforma Of Allotment Letter.Pdf
7 1 Declaration In FORM B.Pdf
8 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
9 1 Commencement Certificates NA Order For Plotted Development.Pdf
10 11 Building Plan Approval NA Order For Plotted Development.Pdf
11 15 Building Plan Approval NA Order For Plotted Development.Pdf
12 14 Building Plan Approval NA Order For Plotted Development.Pdf
13 13 Building Plan Approval NA Order For Plotted Development.Pdf
14 12 Building Plan Approval NA Order For Plotted Development.Pdf
15 10 Building Plan Approval NA Order For Plotted Development.Pdf
16 9 Building Plan Approval NA Order For Plotted Development.Pdf
17 7 Building Plan Approval NA Order For Plotted Development.Pdf
18 6 Building Plan Approval NA Order For Plotted Development.Pdf
19 5 Building Plan Approval NA Order For Plotted Development.Pdf
20 4 Building Plan Approval NA Order For Plotted Development.Pdf
21 3 Building Plan Approval NA Order For Plotted Development.Pdf
22 2 Building Plan Approval NA Order For Plotted Development.Pdf
23 1 Building Plan Approval NA Order For Plotted Development.Pdf
24 8 Building Plan Approval NA Order For Plotted Development.Pdf
25 1 Other – Legal.Pdf
26 1 Declaration About Commencement Certificate.Pdf
27 1 CERSAI Details.Pdf
28 1 Declaration About All RERA Designated Bank Accounts (Format A).Pdf
29 1 Deviation Report With Respect To Allotment Letter.Pdf
30 1 B Details Of Encumbrances Concerned To Legal.Pdf
31 2 B Details Of Encumbrances Concerned To Legal.Pdf
32 1 Other – Finance.Pdf
33 1 Other – Technical.Pdf
34 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
35 1 Proforma Of Agreement For Sale.Pdf
36 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
37 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
38 1 Letter From The Bank Regarding The Opening Of RERA Designated Bank Accounts (Format B).Pdf
39 1 Disclosure For Secured Unsecured Finance Availed For The Project.Pdf
40 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
41 Form 1.Pdf
42 Form 2.Pdf
43 Form 3.Pdf
44 Disclosure Of Sold And Booked Inventory.Pdf
45 Withdrawal Update Form 1.Pdf
52 Withdrawal Update Form 2.Pdf
59 Withdrawal Update Form 3.Pdf
66 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank KOTAK MAHINDRA BANK LIMITED
IFSC KKBK0000958
Branch Address .5 C/ II, MITTAL COURT,224, NARIMAN POINT,MUMBAI - 400 021
Country/City