residential Ready to Move Source: rera.mh

Dreamt Usha Kaal RERA Details - P51800008807, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Dreamt Usha Kaal under registration P51800008807 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800008807
  • Project Name USHA KAAL
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Kurla
  • Village Kurla
  • Original Completion 18 December 2018
  • Revised Completion 18 December 2018
  • Project Area (in Sq.mt.) 449.0
  • Total Buildings/Towers 1
  • Documents 25 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 19 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 18 December 2018 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 18 December 2018 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Individual

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
USHA KAAL USHA KAAL 0 0 9 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 16
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 9 units · avg area 39.80 Sq.mt.
2 BHK 6 units · avg area 58.40 Sq.mt.
4 BHK 1 unit · avg area 158.55 Sq.mt.
  • USHA KAAL
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 29.09 1 0
1BHK 44.5 1 0
4 BHK DUPLEX 158.55 1 0
1 BHK 51.0 3 1
2 BHK 50.09 4 3
2 BHK 75.03 2 0
1BHK 32.9 4 4
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains % not reported Landscaping & Tree Planting 70.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 60.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • USHA KAAL
USHA KAAL · Overall Progress 68%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work63%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work60%
Sanitary Fittings within the flats / premises
In Progress
% Work60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work55%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work50%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 I O D.Pdf.Pdf
2 I O D 1.Pdf.Pdf
3 I O D 2.Pdf.Pdf
4 No Layout.Pdf.Pdf
5 PAN.Pdf.Pdf
6 PAN 1.Pdf.Pdf
7 BUILDING IMAGE.Pdf.Pdf
8 PROPOSE PLAN 2 (1).Pdf.Pdf
9 PROPOSE PLAN 2 (2).Pdf.Pdf
10 Maharera Status.Pdf.Pdf
11 UshaKaal Conpressed.Pdf.Pdf
12 Ushakal.Pdf.Pdf
13 U RERA2 (1).Pdf.Pdf
14 Untitled Compressed.Pdf.Pdf
15 Form B.Pdf.Pdf
16 FORM B 2 (2).Pdf.Pdf
17 FORM B 1.Pdf.Pdf
18 FORM B2.Pdf.Pdf
19 FORM B 2 (1).Pdf.Pdf
20 FORM B 3.Pdf.Pdf
21 FORM B 4.Pdf.Pdf
22 Title.Pdf.Pdf
23 Proforma Of The Allotment Letter And Agreement For Sale 1 (2).Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank NKGSB COOPERATIVE BANK LIMITED
IFSC NKGS0000009
Branch Address Satnam Apartment L T road Mulund East Mumbai 400081
Country/City