Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Sumit One RERA Details - P51800030624, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Sumit One under registration P51800030624 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800030624
  • Project Name Sumit One
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Borivali
  • Village Borivali
  • Original Completion 31 December 2024
  • Revised Completion 31 December 2024
  • Project Area (in Sq.mt.) 1,264.0
  • Total Buildings/Towers 1
  • Documents 14 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 08 September 2021 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Sumit Woods Limited

Promoters, Co-promoters & Members

NameRoleAddress
Bhushan Subodh NemlekarDirectorMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Sumit One Sumit One 0 70 23 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 21
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 2 units · avg area 65.22 Sq.mt.
3 BHK 13 units · avg area 91.65 Sq.mt.
4 BHK 1 unit · avg area 121.96 Sq.mt.
Shop 5 units · avg area 65.81 Sq.mt.
  • Sumit One
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
4BHK 121.96 1 0
Shop 124.95 1 1
Shop 43.66 1 1
2BHK 62.24 1 0
2BHK 68.19 1 1
3BHK 75.62 1 1
Shop 38.28 1 1
3BHK 102.09 5 4
Shop 52.39 1 1
3BHK 86.49 7 7
Shop 69.77 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains 60.0% Landscaping & Tree Planting 90.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 90.0%
Electrical Meter Room, Sub-station, Receiving Station 80.0% Aggregate Area Of Recreational Open Space 90.0% Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Sumit One
Sumit One · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Approved Plan Sheet 6.Pdf.Pdf
2 IOD 23112020 19082021.Pdf.Pdf
3 Approved Plan Sheet 1.Pdf.Pdf
4 Approved Plan Sheet 2.Pdf.Pdf
5 Approved Plan Sheet 3.Pdf.Pdf
6 Approved Plan Sheet 4.Pdf.Pdf
7 Approved Plan Sheet 5.Pdf.Pdf
8 NA Payment Receipt And Order.PDF.Pdf
9 Development Agreement Wagle Society To Sumit Woods Compressed.Pdf.Pdf
10 Title Certificate 22072021 SumitOne.Pdf.Pdf
11 Affidavit Cum Declaration Sumit One.Pdf.Pdf
12 Sumit One Sale Agreement.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0000281
Branch Address Shagun Mall Goregaon East
Country/City