Goregaon Sukhniwas CHS RERA Details - P51800028730, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Goregaon Sukhniwas CHS under registration P51800028730 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800028730
  • Project Name GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Borivali
  • Village Borivali
  • Original Completion 30 June 2024
  • Revised Completion 30 June 2024
  • Project Area (in Sq.mt.) 556.7
  • Total Buildings/Towers 1
  • Documents 26 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 25 March 2021 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Individual

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED 0 36 25 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 74
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 38 units · avg area 44.24 Sq.mt.
2 BHK 36 units · avg area 60.26 Sq.mt.
  • GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 60.26 36 28
1BHK 44.24 38 30
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 60.0%
Electrical Meter Room, Sub-station, Receiving Station 40.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED
GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED · Overall Progress 92%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work90%
Sanitary Fittings within the flats / premises
In Progress
% Work50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work70%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 21 Iod Part 1.Pdf.Pdf
2 21 Iod Part 2.Pdf.Pdf
3 21 Iod Drawings 1.Pdf.Pdf
4 21 Iod Drawings 2.Pdf.Pdf
5 21 Iod Drawings 3.Pdf.Pdf
6 21 Iod Drawings 4.Pdf.Pdf
7 SUKHNIWAS Iod 11 To 19 Floor Part 1 Compressed.Pdf.Pdf
8 SUKHNIWAS Iod 11 To 19 Floor Part 2.Pdf.Pdf
9 Dilip Doshi Pan Card.Pdf.Pdf
10 PR Card (1).Pdf.Pdf
11 Structural Stability Sukhnivas.Pdf.Pdf
12 Power Of Attorney Building No 21 Sukhnivas (1) (1).Pdf.Pdf
13 PART 2 DEVELOPMENT AGREEMENT.Pdf.Pdf
14 PART 1 DEVELOPMENT AGREEMENT.Pdf.Pdf
15 LEASE DEED SUKHNIVAS.Pdf.Pdf
16 Sale Deed SukhnivaS.Pdf.Pdf
17 Poa.Pdf.Pdf
18 Pan Card.Pdf.Pdf
19 Adhar Card.Pdf.Pdf
20 Death Cert.Pdf.Pdf
21 Title Certificate Sukhniwas Compressed.Pdf.Pdf
22 Legal Tiltle Report Sukhniwas Rera.Pdf.Pdf
23 Form B Compressed.Pdf.Pdf
24 Sukhniwas Agreement Edited As On 25 Feb 2021.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BANK OF BARODA
IFSC BARB0GOREGA
Branch Address GOREGOAN WEST
Country/City