residential Under Construction Source: rera.mh

Hiranandani Vista Residences RERA Details - P51800076720, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Hiranandani Vista Residences under registration P51800076720 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800076720
  • Project Name VISTA RESIDENCES WING C TOWER 2
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Borivali
  • Village Goregaon
  • Original Completion 30 June 2029
  • Revised Completion 30 June 2029
  • Project Area (in Sq.mt.) 736.5
  • Total Buildings/Towers 1
  • Documents 5 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 21 June 2024 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2029 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2029 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name VISTA DEVELOPERS MUMBAI LLP
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
VISTA RESIDENCES WING D TOWER -3NEW LINK ROAD VILLAGE GOREGAON GOREGAON WEST MUMBAI 400102419.07OngoingResidential / Group Housing11062028-12-312028-12-31NoNA

Promoters, Co-promoters & Members

NameRoleAddress
DOSTMOHAMMED HAJI VALLI PATELPartnerMumbai City, MAHARASHTRA
SAJID YAKUB PATELPartnerMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
VISTA RESIDENCES WING C TOWER 2 VISTA RESIDENCES WING C TOWER -2 0 192 35 8 25 106 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 106
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 65 units · avg area 73.86 Sq.mt.
3 BHK 37 units · avg area 103.23 Sq.mt.
Penthouse 4 units · avg area 300.00 Sq.mt.
  • VISTA RESIDENCES WING C TOWER -2
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Penthouse 300.0 4 0
2BHK 83.57 2 0
2BHK 71.19 19 3
2BHK 74.48 39 4
3BHK 103.23 37 7
2BHK 72.04 2 1
2BHK 82.5 1 1
2BHK 74.85 2 2
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • VISTA RESIDENCES WING C TOWER -2
VISTA RESIDENCES WING C TOWER -2 · Overall Progress 41%
Excavation
Complete
% Work100%
Basement (if any)
In Progress
% Work85%
Podiums (if any)
In Progress
% Work71%
Plinth
Complete
% Work100%
Stilt Floor
In Progress
% Work95%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
70 Withdrawal Update Form 1.Pdf
73 Withdrawal Update Form 2.Pdf
76 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0000060
Branch Address GROUND FLOOR, JEHANGIR BUILDING, M G MARG, FORT, MUMBAI 400 001
Country/City