Hirani Swanand Oasis RERA Details - P51800004914, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Hirani Swanand Oasis under registration P51800004914 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800004914
  • Project Name SWANAND BLDG NO 33
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Kurla
  • Village Kurla
  • Original Completion 31 December 2019
  • Revised Completion 30 November 2024
  • Project Area (in Sq.mt.) 1,308.93
  • Total Buildings/Towers 1
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2019 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 November 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name HIRANIMANTHAN BUILDERS AND DEVELOPERS
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
ANTARIKSH CHSANTARIKSH CHS BUILDING NO 43 NEHRU NAGAR KURLA EAST MUMBAI 400024 1219CompletedResidential / Group Housing3752008-02-012008-03-28NoNA
MEGHDOOT CHSMEGHDOOT CHS BUIDLING NO 73 NEHRU NAGAR KURLA EAST MUMBAI 400024965.83CompletedResidential / Group Housing2512010-11-252010-12-16NoNA

Promoters, Co-promoters & Members

NameRoleAddress
DINESH SAVANTPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SWANAND BLDG NO 33 SWANAND CHS, BLDG NO 33 0 28 21 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 89
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1RK 1 unit · avg area 31.02 Sq.mt.
1 BHK 56 units · avg area 44.98 Sq.mt.
2 BHK 32 units · avg area 59.89 Sq.mt.
  • SWANAND CHS, BLDG NO 33
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1RK 31.02 1 0
2BHK 52.33 1 0
1BHK 45.29 16 15
1BHK 45.79 7 3
1BHK 44.03 1 1
2BHK 60.13 31 28
1BHK 44.67 32 29
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 95.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 95.0%
Storm Water Drains 95.0% Landscaping & Tree Planting 90.0% Street Lighting 90.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal 90.0%
Water Conservation /Rain Water Harvesting 90.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 90.0%
Electrical Meter Room, Sub-station, Receiving Station 90.0% Aggregate Area Of Recreational Open Space % not reported Open Parking 90.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SWANAND CHS, BLDG NO 33
SWANAND CHS, BLDG NO 33 · Overall Progress 91%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank INDIAN OVERSEAS BANK
IFSC IOBA0000584
Branch Address RAJESH BIULDING CHANDAVARKAR ROAD BORIVALI WEST MIUMBAI
Country/City